Question

Capiz Corporation uses the two-way overhead variance analysis. During the recently ended period, total controllable variance...

Capiz Corporation uses the two-way overhead variance analysis. During the recently ended period, total controllable variance was determined to be at P16,000 unfavorable while total non-controllable variance was at P6,000 favorable. Total actual factory overhead amounted to P3,530,000. Actual production totaled 352,000 units while standard machine hours per unit produced is 2 hours. Total budgeted capacity is 700,000 machine hours.

a. How much is the total overhead applied to actual production?

b. What is the standard overhead rate per hour?

c. What is the budgeted fixed overhead?

d. What is the standard variable rate per hour?

Homework Answers

Answer #1

Solution a:

Budgeted overhead for actual production = Actual factory overhead - Unfavorable controllable variance

= 3,530,000 - 16,000 = 3,514,000

Total overhead applied = Budgeted overhead + Favorable non controllable variance = 3,514,000 + 6,000 = 3,520,000

Solution b:

Standard overhead rate per hour = Overhead applied / Standard hours

= 3,520,000 / (352000*2) = $5 per machine hour

solution c:

Budgeted overhead = 700000*$5 = 3,500,000

Budgeted overhead for actual production = 3,514,000

Variable overhead rate = (3,514,000 - 3,500,000) / (704000 - 700000) = $3.50 per machine hour

Budgeted fixed overhead = $3,500,000 - (700000*$3.50) = $1,050,000

Solution d:

Standard variable rate per hour = $3.50 per machine hour

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 3,000 computers: Actual: Variable factory overhead $122,200 Fixed factory overhead 35,000 Standard: 3,000 hrs. at $49 147,000 If productive capacity of 100% was 5,000 hours and the total factory overhead cost budgeted at the level of 3,000 standard hours was $161,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $90,200 Fixed factory overhead 34,500 Standard: 4,000 hrs. at $29 116,000 If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $127,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Controllable Variance Bellingham Company produced 4,300 units of product that required 8.5 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 4,300 units of product that required 8.5 standard hours per unit. The standard variable overhead cost per unit is $6.00 per hour. The actual variable factory overhead was $210,970. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $ Favorable
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory overhead 38,500 Standard: 7,000 hrs. at $18 126,000 If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $65,000 Fixed factory overhead 25,500 Standard: 4,000 hrs. at $21 84,000 If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $92,500, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $297,100 Fixed factory overhead 68,750 Standard: 7,000 hrs. at $50 350,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $375,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $223,100 Fixed factory overhead 94,250 Standard: 8,000 hrs. at $36 288,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $324,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $7.25 per hour....
Factory Overhead Controllable Variance Bellingham Company produced 6,400 units of product that required 3.5 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 6,400 units of product that required 3.5 standard hours per unit. The standard variable overhead cost per unit is $5.80 per hour. The actual variable factory overhead was $135,250. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $ Factory Overhead Volume Variance Dvorak Company produced 2,400 units of product that required 4 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 3,700 units of product that required 1.5 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 3,700 units of product that required 1.5 standard hours per unit. The standard variable overhead cost per unit is $5.00 per hour. The actual variable factory overhead was $28,420. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $  
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $97,000 Fixed factory overhead 32,000 Standard: 5,000 hrs. at $24 120,000 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $132,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...