Question

1. The following information concerns production in the Finishing Department for May. The Finishing Department uses...

1. The following information concerns production in the Finishing Department for May. The Finishing Department uses the Weighted average method.

ACCOUNT Work in Process—Finishing Department ACCOUNT NO.
Date Item Debit Credit Balance
Debit Credit
May 1 Bal., 12,400 units, 65% completed 37,200
31 Direct materials, 60,800 units 111,264 148,464
31 Direct labor 69,000 217,464
31 Factory overhead 70,100 287,564
31 Goods transferred, 64,500 units 276,705 10,859
31 Bal., ? units, 25% completed 10,859

a. Determine the number of units in work in process inventory at the end of the month.
_________  units

b. Determine the number of whole units to be accounted for and to be assigned costs and the equivalent units of production for May. Assume that direct materials are placed in process during production.

Whole units to be accounted for
Whole units to be assigned costs   
Equivalent units of production

2. The Mountain Springs Water Company has two departments, Purifying and Bottling. The Bottling Department received 68,740 liters from the Purifying Department. During the period, the Bottling Department completed 65,850 liters, including 2,770 liters of work in process at the beginning of the period. The ending work in process was 5,660 liters. How many liters were started and completed during the period?
_________ liters started and completed

3. In the manufacture of 9,100 units of a product, direct materials cost incurred was $174,600, direct labor cost incurred was $108,700, and applied factory overhead was $49,900. What is the total conversion cost?

a.$174,600

b.$333,200

c.$49,900

d.$158,600

Homework Answers

Answer #1

a. Determine the number of units in work in process inventory at the end of the month.
12400+60800-64500 = 9100 units

b. Determine the number of whole units to be accounted for and to be assigned costs and the equivalent units of production for May. Assume that direct materials are placed in process during production.

Whole units to be accounted for 12800+60800 = 73600
Whole units to be assigned costs 73600
Equivalent units of production 64500+9100*25% = 66775

2.) Unit started and completed = 65850-2770 = 63080 liters

3) Total conversion Cost = Direct labor and overhead = 108700+49900 = 158600

So answer is d) $158600

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Equivalent Units of Production: Weighted average method The following information concerns production in the Finishing Department...
Equivalent Units of Production: Weighted average method The following information concerns production in the Finishing Department for May. The Finishing Department uses the Weighted average method. ACCOUNT Work in Process—Finishing Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit May 1 Bal., 22,700 units, 70% completed 113,500 31 Direct materials, 111,200 units 339,160 452,660 31 Direct labor 210,300 662,960 31 Factory overhead 213,700 876,660 31 Goods transferred, 118,000 units 843,700 32,960 31 Bal., ? units, 30% completed 32,960 a....
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Mar. 1 Bal., 4,800 units, 2/3 completed 6,080 31 Direct materials, 86,400 units 164,160 170,240 31 Direct labor 44,690 214,930 31 Factory overhead 25,134 240,064 31 Goods finished, 87,600 units 230,920 9,144 31 Bal. ? units, 4/5 completed 9,144...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March 1 Bal., 7,800 units, 2/5 completed 24,960 31 Direct materials, 140,400 units 224,640 249,600 31 Direct labor 64,460 314,060 31 Factory overhead 36,256 350,316 31 Goods finished, 142,200 units 337,356 12,960 31 Bal. ? units, 4/5 completed 12,960...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March 1 Bal., 6,300 units, 3/5 completed 25,200 31 Direct materials, 113,400 units 226,800 252,000 31 Direct labor 65,110 317,110 31 Factory overhead 36,626 353,736 31 Goods finished, 114,900 units 342,408 11,328 31 Bal. ? units, 2/5 completed 11,328...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March. 1 Bal., 7,800 units, 4/5 completed 28,080 31 Direct materials, 140,400 units 252,720 280,800 31 Direct labor 70,840 351,640 31 Factory overhead 39,848 391,488 31 Goods finished, 142,200 units 378,768 12,720 31 Bal. ? units, 2/5 completed 12,720...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March 1 Bal., 5,700 units, 3/5 completed 20,520 31 Direct materials, 102,600 units 184,680 205,200 31 Direct labor 53,270 258,470 31 Factory overhead 29,962 288,432 31 Goods finished, 104,100 units 278,184 10,248 31 Bal. ? units, 4/5 completed 10,248...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March. 1 Bal., 6,600 units, 2/5 completed 21,120 31 Direct materials, 118,800 units 190,080 211,200 31 Direct labor 54,080 265,280 31 Factory overhead 30,424 295,704 31 Goods finished, 120,300 units 285,402 10,302 31 Bal. ? units, 3/5 completed 10,302...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March. 1 Bal., 6,300 units, 3/5 completed 16,380 31 Direct materials, 113,400 units 147,420 163,800 31 Direct labor 43,410 207,210 31 Factory overhead 24,414 231,624 31 Goods finished, 114,900 units 224,232 7,392 31 Bal. ? units, 2/5 completed 7,392...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All...
Equivalent Units of Production The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March. 1 Bal., 8,100 units, 2/5 completed 30,780 31 Direct materials, 145,800 units 277,020 307,800 31 Direct labor 75,850 383,650 31 Factory overhead 42,662 426,312 31 Goods finished, 147,600 units 411,318 14,994 31 Bal. ? units, 3/5 completed 14,994...
The following information concerns production in the Baking Department for March. All direct materials are placed...
The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit March 1 Bal., 4,500 units, 3/5 completed 13,500 31 Direct materials, 81,000 units 121,500 135,000 31 Direct labor 36,500 171,500 31 Factory overhead 20,536 192,036 31 Goods finished, 82,200 units 185,700 6,336 31 Bal. ? units, 3/5 completed 6,336 a. Determine the number...