11. Direct Materials cost is debited to: a.
Raw Materials Inventory b. Manufacturing
Overhead c. Cost of Goods
Sold d. Direct Materials
e. Work in Process
____12. Beginning Finished Goods Inventory + X – Ending Finished
Goods Inventory = Cost of Goods Sold. What is
X? a. Direct Materials b.
Manufacturing Overhead c. Cost of Goods
Manufactured d. Beginning Work in Process
Inventory
____13. One way to calculate the Predetermined Overhead Rate is:
a. estimated MO divided by estimated Direct Labor
Cost b. actual MO divided by actual Direct
Labor cost c. actual Direct Labor cost divided by
actual MO d. actual MO divided by applied MO
_____14. Depreciation on the salesman’s automobile would be debited
to: a. depreciation expense b.
manufacturing overhead c. indirect labor
cost d. finished goods inventory
____15. What criterion must be satisfied for inventory costs to
move from Work in Process to Finished Goods
Inventory? A. the goods get
sold B. the manufacturing overhead is
applied C. the goods get finished D. the goods
get damaged
____16. What criterion must be satisfied for inventory costs to move from Finished Goods to Cost of Goods Sold? A. the goods get sold B. the manufacturing overhead is applied C. the goods get finished D. a requisition is approved
Solution 11:
Direct Materials cost is debited to "Work in Process"
Hence option e is correct.
Solution 12:
Beginning Finished Goods Inventory + Cost of Goods Manufactured – Ending Finished Goods Inventory = Cost of Goods Sold.
Hence option c is correct.
Solution 13:
One way to calculate the Predetermined Overhead Rate is "estimated MO divided by estimated Direct Labor Cost"
Hence option a is correct.
Solution 14:
Depreciation on the salesman’s automobile would be debited to "Depreciation expense"
Hence option a is correct
Solution 15:
Criterion that must be satisfied for inventory costs to move from Work in Process to Finished Goods Inventory is "The goods get finished"
Hence option c is correct.
Solution 16:
Criterion that must be satisfied for inventory costs to move from Finished Goods to Cost of Goods Sold is "The goods get sold"
Hence option a is correct.