Question

WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials...

WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data:

Direct Materials 12 pounds @ $ 2.00 per pound

Direct Labor   2 DLH @ $15.00 per DLH

Variable MOH   1 MHR @ $10.00 per MHR

Fixed MOH   1 MHR @ $20.00 per MHR

Production was forecast to be 2,000 units, but only 1,950 were actually produced. 26,000 pounds of materials were purchased for $66,300. A total of 23,000 pounds of materials were used in production. Actual direct labor totaled 4,000 DLH, costing $48,000. Forecast variable overhead was $10,000, and forecast fixed overhead was $40,000. Actual variable overhead was $11,000. Actual fixed overhead was $38,000. Actual machine hours totaled 1,900 MHR.

16THE ANSWER IS e11. (5 POINTS) Calculate the direct materials price variance. ANSWER: __________________

17THE ANSWER IS e11. (5 POINTS) Calculate the direct materials usage variance. ANSWER: ___________________

18THE ANSWER IS e11. (5 POINTS) Calculate the direct labor efficiency variance. ANSWER: ___________________

19THE ANSWER IS e11. (5 POINTS) Calculate the direct labor rate variance. ANSWER: _________________

Homework Answers

Answer #1

16.DIRECT MATERIAL PRICE VARIANCE = (STANDARD PRICE * ACTUAL QUANDITY) - (ACTUAL PRICE * ACTUAL QUANDITY) = (2 * 23000) - (58650) = 46000 - 58650 = 12650 ADVERSE

17.DIRECT MATERIAL USAGE VARIANCE = (STANDARD QUANDITY - ACTUAL QUANDITY) * STANDARD PRICE

= ( 12*1950 - 23000) * 2 = 800 FAVORABLE

18.DIRECT LABOUR EFFICIENCY VARIANCE = (STANDARD HOURS - ACTUAL HOURS) * STANDARD RATE =

(2*1950 - 4000) * 15 = 1500 ADVERSE

19.DIRECT LABOUR RATE VARIANCE = ( STANDARD RATE - ACTUAL RATE ) * ACTUAL HOURS

= (15 - 12) * 4000 = 12000 FAVOURABLE

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials  ...
WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials   12 pounds             @            $ 2.00 per pound Direct Labor         2 DLH                 @            $15.00 per DLH Variable MOH     1 MHR                @            $10.00 per MHR Fixed MOH          1 MHR                @            $20.00 per MHR Production was forecast to be 2,000 units, but only 1,950 were actually produced. 26,000 pounds of materials were purchased for $66,300. A total of 23,000 pounds of materials were used...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
Mike Manufacturing has the following standard cost sheet for one of its products: Direct materials (6...
Mike Manufacturing has the following standard cost sheet for one of its products: Direct materials (6 ft. @ $5) $30 Direct labour (1.5 hours @$10) 15 Variable overhead (1.5 hours@ $4) 6 Fixed overhead (1.5 hours@ $2*) 3 Standard unit cost 54 The rate based on expected activity of 17,000 hours. During the most recent year, the following actual results were recorded: Production 12,000 units Fixed overhead $33,000 Variable overhead $69,000 Direct materials (71,750 ft. purchased) $361,620 Direct labour (17,900...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per costume12.50yards,, Price per yard $26.00average Direct Labor: D.L. Hours per costume 62.00hours,, D.L. Rate per hour $44.50average Variable MOH standard rate per direct labor hour $4.35per D.L. hour,,Fixed MOH standard rate per direct labor hour $9.47per D.L. hour,,Total Budgeted Fixed MOH (for 1 month) $ 1,250,000 Actual cost and data from the current month: Actual number of yards of materials purchased 28,500 Actual cost...
Nosemer Company produces engine parts for large motors. The company uses a standard cost system for...
Nosemer Company produces engine parts for large motors. The company uses a standard cost system for production costing and control. The standard cost sheet for one of its higher volume products (a valve), is as follows: Direct materials (5 lbs. @ $4.00) $20.00 Direct labor (1.4 hrs. @ $10.50) 14.70 Variable overhead (1.4 hrs. @ $6.00) 8.40 Fixed overhead (1.4 hrs. @ $3.00) 4.20 Standard unit cost $47.30 During the year, Nosemer experienced the following activity relative to the produc-...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget...
6-25 Comprehensive variance calculations (LO 2, 4, 6, 7) Carson Construction Consultants performs cement core tests...
6-25 Comprehensive variance calculations (LO 2, 4, 6, 7) Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company's controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound    4 pounds $ 2.00 Direct labor $10 per DLH   .5 DLH   5.00 Variable overhead $9 per DLH   .5 DLH   4.50 Fixed overhead $16 per DLH   ...
Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for...
Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used 630 hrs. Actual rate for direct labor $11.70 per hr. Bicycles completed in October 300 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.90 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a...
Plummer Corporation makes a product with the following standard costs: Inputs Standard Quantity or Hours Standard...
Plummer Corporation makes a product with the following standard costs: Inputs Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 4.3 pounds $6.00 per pound $25.80 Direct labor 0.7 hours $20.00 per hour $14.00 Variable overhead 0.7 hours $2.00 per hour $1.40    The company reported the following results concerning this product in August. Originally budgeted output 1,900 units Actual output 1,700 units Raw materials used in production 7,210 pounds Purchases of raw materials 7,210...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT