Swifty Company identifies three activities in its manufacturing
process: machine setups, machining, and inspections. Estimated
annual overhead cost for each activity is $205,900, $411,200, and
$58,500, respectively. The cost driver for each activity and the
estimated annual usage are number of setups 2,900, machine hours
25,700, and number of inspections 1,300.
Compute the overhead rate for each activity.
Machine setups |
$enter a dollar amount per setup |
per setup | |
---|---|---|---|
Machining |
$enter a dollar amount per machine hour |
per machine hour | |
Inspections |
$enter a dollar amount per inspection |
per inspection |
Solution
Activity rate | ||
Machine setup | $ 71.00 | Per setup |
Machining | $ 16.00 | Per Machine hour |
Inspections | $ 45.00 | Per inspection |
Working.
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Machine setup | Number of setup | $ 205,900 | 2900 | $ 71.00 | Per setup |
Machining | Number of Machine hour | $ 411,200 | 25700 | $ 16.00 | Per Machine hour |
Inspections | Number of inspection | $ 58,500 | 1300 | $ 45.00 | Per inspection |
.