Question

Machine Master, Inc. had the following data regarding monthly power costs: Month Machine hours Power cost...

  1. Machine Master, Inc. had the following data regarding monthly power costs:

Month

Machine hours

Power cost

Jan

300

$650

Feb

600

720

Mar

400

685

Apr

200

640

May

350

675

  1. Use the high-low method, estimate the cost formula regarding monthly power costs
  1. Assume that management expects 500 machine hours in May. Calculate May’s power cost using machine hours as the basis for prediction.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 1 Harbour Inc. collected the following data for the first six months of the year...
Question 1 Harbour Inc. collected the following data for the first six months of the year concerning its overhead costs and machine hours used. Month Overhead Costs ($) Machine Hours Jan $62,000 400 Feb 52,000 320 Mar 64,000 395 Apr 58,000 350 May 57,000 350 June 54,000 325 Required - a)            Harbour suspects that machine hours are driving overhead costs. Use the high-low method to calculate the: i.             variable cost per machine hour; ii.                monthly fixed cost. b)           Harbour predicts that...
Bay Co. has accumulated data to use in preparing its annual profit plan for the upcoming...
Bay Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year are as follows: Month Maintenance Cost ($) Machine Hours Jan. 5040 620 Feb. 3600 420 Mar. 4320 520 Apr. 3380 390 May 5220 650 June 3550 400 July 3640 430 Aug. 5360 680 Sept. 5110 640 Oct. 4860 610 Nov....
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,950 780 Feb. 3,750 620 Mar. 4,350...
Uptop Mining has compiled the following data to analyze utility costs: Month Machine Hours Utility Cost...
Uptop Mining has compiled the following data to analyze utility costs: Month Machine Hours Utility Cost January 200 300 February 325 440 March 400 480 April 410 490 May 525 620 June 680 790 July 820 840 August 900 900 Use the least square method to develop a formula for budgeting utility cost. *Don't us excel or any other software to solve this problem.
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,200 480 Feb. 3,000 320 Mar. 3,600...
The controller of Norton Industries has collected the following monthly expense data for use in analyzing...
The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,930 350 February 3,230 400 March 3,830 550 April 4,730 640 May 3,430 550 June 5,840 750 Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g. 12.250.) Determine the fixed cost components using the high-low method. (Round answer to 0 decimal places...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,800 720 Feb. 3,600 560 Mar. 4,200...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming...
Armer Company is accumulating data to use in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested the use of linear regression to derive an equation for maintenance hours and costs. Data regarding the maintenance hours and costs for the last year and the results of the regression analysis follow: Month Maintenance Cost Machine Hours Jan. $ 4,750 700 Feb. 3,550 540 Mar. 4,150...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year and the results of the regression analysis are as follows: Month Maintenance Cost Machine Hours Jan. $ 5,040 620 Feb. 3,600 420 Mar. 4,320 520 Apr. 3,380 390 May 5,220 650 June 3,550 400 July 3,640 430 Aug. 5,360 680...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming...
Burmer Co. has accumulated data to use in preparing its annual profit plan for the upcoming year. The cost behavior pattern of the maintenance costs must be determined. Data regarding the machine hours and maintenance costs for the last year and the results of the regression analysis are as follows: Month Maintenance Cost Machine Hours Jan. $ 5,040 620 Feb. 3,600 420 Mar. 4,320 520 Apr. 3,380 390 May 5,220 650 June 3,550 400 July 3,640 430 Aug. 5,360 680...