Question

part 1) The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and...

part 1)

The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected.

Group of answer choices

true

false

part 2

Cost Performance Index (CPI) can be used a tool to project the total estimated project cost at completion. If a project's original estimate (budget) was $2,400,500 and the CPI you just calculated is 1.07, what would be the total estimated project cost at completion?

Group of answer choices

$2,568,535

$2,243,458

$2,400,500

Homework Answers

Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected.
This statement is true.
Part 2 Amount $ Note
Project's original estimate (budget)    2,400,500.00 A
CPI 1.07 B
Total estimated project cost at completion 2,568,535.00 C=A*B
So answer is $ 2,568,535.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
part 1) The first step should be taken when doing a project closeout audit is: Group...
part 1) The first step should be taken when doing a project closeout audit is: Group of answer choices identifying project success factors (areas where project performed better than expected). identifying the areas of the project where problems took place. validating the project costing data and making sure that costs were coded to the appropriate project and cost codes and all costs have been accounted for. calculating the Cost Performance Index (CPI) PART 2) A Cost Performance Index (CPI) greater...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
1) Which of the following is not a valid way that a CRM system can collect...
1) Which of the following is not a valid way that a CRM system can collect information? A. accounting system B. order fulfillment system C. inventory system D. customer’s personal computer 2)Which of the following is a common marketing CRM metric? A. number of new prospective customers B. average number of service calls per day C. average time to resolution D. cost per interaction by marketing campaign 3)Which question below represents a CRM reporting technology example? A. Why did sales...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
The questions: 1. What type of technology Acme and Omega utilize to transform inputs into outputs?...
The questions: 1. What type of technology Acme and Omega utilize to transform inputs into outputs? 2. Which strategic choice (differentiation or cost leadership) suits best to Acme? Omega? Do these companies have clear strategic choices or do they stuck in the middle? 3. Based on all the contingencies which type of structure is more suitable for these companies; mechanistic or organic? please answer each question alone The Paradoxical Twins: Acme and Omega Electronics John F. Veiga Part! boom of...