part 1)
The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected.
Group of answer choices
true
false
part 2
Cost Performance Index (CPI) can be used a tool to project the total estimated project cost at completion. If a project's original estimate (budget) was $2,400,500 and the CPI you just calculated is 1.07, what would be the total estimated project cost at completion?
Group of answer choices
$2,568,535
$2,243,458
$2,400,500
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected. |
This statement is true. |
Part 2 | Amount $ | Note |
Project's original estimate (budget) | 2,400,500.00 | A |
CPI | 1.07 | B |
Total estimated project cost at completion | 2,568,535.00 | C=A*B |
So answer is $ 2,568,535. |