Question

Azalea Company began construction on a new office building on Jan. 1 of this year. The...

Azalea Company began construction on a new office building on Jan. 1 of this year. The building was completed on Sept. 30. Expenditures were made of $200,000 on Jan. 1; $300,000 on Sept. 1; and $300,000 on Dec. 31. The weighted average accumulated expenditures are:

Group of answer choices

$500,000

$300,000

$350,000

$400,000

Homework Answers

Answer #1

Answer: $300,000

Explanation

Calculation of The weighted average accumulated expenditures
Date Actual Capitalization Weighted Average
Expenditure Period Accumulated Expenditure
Jan. 1 $ 200,000.00 12/12 $                      200,000.00
Sept. 1 $ 300,000.00 4/12 $                      100,000.00
Dec. 31 $ 300,000.00 0/12 $                                   -  
$ 300,000.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Oriole Company is constructing a building. Construction began in 2020 and the building was completed 12/31/20....
Oriole Company is constructing a building. Construction began in 2020 and the building was completed 12/31/20. Oriole made payments to the construction company of $3054000 on 7/1, $6336000 on 9/1, and $5920000 on 12/31. Weighted-average accumulated expenditures were
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
XYZ Corp began construction on a building on January 1, 2016. On that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use. To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its...
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $258,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 275,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was outstanding for the...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, ABC Company began construction of a building to be used as its...
On January 1, 2018, ABC Company began construction of a building to be used as its warehouse. The building was completed on November 1, 2019. Expenditures for the project during 2018 were as follows: January 1, 2018 900,000 April 1, 2018 700,000 July 1, 2018 650,000 October 1, 2018 840,000 On January 1, 2018, ABC Company obtained a $4,000,000 construction loan with 9% interest rate payable in 5 years. The Company’s other debts included a note of $1,000,000 at 11%...