Question

Question 1 A company manufactures a single product for which the standard variable cost is:                            

Question 1

A company manufactures a single product for which the standard variable cost is:

                                                                         K per unit

Direct material: 81 kg x K7 per kg                            567

Direct labour:    97 hours x K8 per hour                   776

Variable overhead: 97 hours x K3 per hour              291

                                                                               1,634

Budget

Sales and production volume                   81,600 units

Standard selling price                               K59 per unit

Standard variable cost                             K24 per unit

During January, 530 units were produced and the costs incurred were as follows:

Direct material: 42,845 kg purchased and used; cost K308,484

Direct labour: 51,380 hours worked; cost K400,764

Variable overhead: cost K156,709

Actual results

Sales and production volume                     82,400 units

Actual selling price                                     K57 per unit

Actual variable cost                                    K23 per unit

Required:

(a) Calculate the following variances

  1. Direct material total variance
  2. Direct labour rate variance
  3. Direct labour efficiency variance
  4. Sales price variance
  5. Sales volume contribution variance                                                                                                                                                         

(b) Discuss the three (3) Performance Levels in Standard Costing                                                                                                      

(c) Discuss three (3) criticisms levelled against the appropriateness of Standard Costing in the Modern Environment

                                                                                                               

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) Pardoe Inc., manufactures a single product in which variable manufacturing overhead is assigned on the...
1) Pardoe Inc., manufactures a single product in which variable manufacturing overhead is assigned on the basis of standard direct labor-hours. The company uses a standard cost system and has established the following standards for one unit of product: Standard Quantity Standard Price or Rate Standard Cost Direct materials 1.5 pounds $3.00 per pound $4.50 Direct labor 0.6 hours $6.00 per hour $3.60 Variable manufacturing overhead 0.6 hours $1.25 per hour $0.75 During March, the following activity was recorded by...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard cost per unit $ 105.00 The company planned to produce and sell 19,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $10.00 per kg $ 50.00 Direct labour: 4 hours at $16 per hour 64.00 Variable overhead: 4 hours at $7 per hour 28.00 Total standard cost per unit $ 142.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
The Clark Company makes a single product and uses standard costing. Some data concerning this product...
The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow: Labour rate variance $7,000 favourable Labour efficiency variance $12,000 favourable Variable overhead efficiency variance $4,000 favourable Number of units produced 10,000 Standard labour rate per direct labour hour $12 Standard variable overhead rate per direct labour hour $4 Actual labour hours used 14,000 Actual variable manufacturing overhead costs $58,290 1) What was the variable overhead spending variance for...
Question 4 – Standard Costing (10 marks) The standard cost of making a single product is:...
Question 4 – Standard Costing The standard cost of making a single product is: 5kg @$2.75 per kg 13.75 0.4 hours @$6.40 per hour 2.56. Factory overhead 0.4 hours @3.50 per hour 1.400 $17.71 The factory overhead rate is based on a budgeted production of 20,000 units for the year, and budgeted fixed factory overhead of $12,000 for the month. Actual transactions and results for the year were: Direct Materials purchased 200,000kgs @ 2.78 per kg Direct Materials used 101,800...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $8.00 per kg $ 40.00     Direct labour: 3 hours at $15 per hour 45.00     Variable overhead: 3 hours at $9 per hour 27.00     Total standard cost per unit $ 112.00   The company planned to produce and sell 21,000 units in March. However, during March the company actually produced and...
Bronfenbrenner Co. uses a standard cost system for its single product in which variable overhead is...
Bronfenbrenner Co. uses a standard cost system for its single product in which variable overhead is applied on the basis of direct labor hours. The following information is given: Standard costs per unit: Raw materials (1.5 grams × $16 per gram) $24.00 Direct labor (0.75 hours × $8 per hour) $6.00 Variable overhead (0.75 hours × $3 per hour) $2.25 Actual experience for current year: Units produced 22,400 units Purchases of raw materials (21,000 grams × $17 per gram) $357,000...
The following is information related to X Company, a company that uses a standard cost system:...
The following is information related to X Company, a company that uses a standard cost system: Standard cost card for 1 unit of Product A: Direct materials – Raw Material A (1 kilogram @ $ 20/kg.) $ 20 Direct materials – Raw Material B (1 kilogram @$ 10/kg.) $ 10 Direct labour (1 hour @ $15/hr.) $ 15 V ariable overhead (1 hour @ $ 5/hr.) $ 5 Fixed overhead (1 hour @ $ 10/hr.) $ 10 Total budgeted fixed...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $384,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $4.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.20 per hour. The company planned to operate at a...
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $11.00 per kg $ 55.00   Direct labour: 3 hours at $12 per hour 36.00   Variable overhead: 3 hours at $7 per hour 21.00   Total standard cost per unit $ 112.00   The company planned to produce and sell 21,000...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT