Question

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory:

Purchase price of the land

$

1,290,000

Demolition and removal of old building

89,000

Clearing and grading the land before construction

195,000

Various closing costs in connection with acquiring the land

51,000

Architect's fee for the plans for the new building

59,000

Payments to Maxtor for building construction

3,340,000

Equipment purchased

905,000

Freight charges on equipment

41,000

Trees, plants, and other landscaping

54,000

Installation of a sprinkler system for the landscaping

5,900

Cost to build special platforms and install wiring for the equipment

21,000

Cost of trial runs to ensure proper installation of the equipment

7,900

Fire and theft insurance on the factory for the first year of use

33,000

  
In addition to the above expenditures, Teradene purchased four forklifts from Caterpillar. In payment, Teradene paid $25,000 cash and signed a noninterest-bearing note requiring the payment of $79,000 in one year. An interest rate of 6% properly reflects the time value of money for this type of loan.

Required:
Determine the initial valuation of each of the assets Teradene acquired in the above transactions. (Round your answers to the nearest whole dollars.)

Homework Answers

Answer #1
Initial Valuation
Land 1625000
Building 3399000
Equipment 974900
Land improvements 59900
Fork lifts 99529
Prepaid insurance 33000

Working:

Land
Purchase price of the land 1290000
Demolition and removal of old building 89000
Clearing and grading the land 195000
Closing costs 51000
Total cost $ 1625000
Building
Architect's fee 59000
Payments to Maxtor 3340000
Total cost $ 3399000
Equipment
Purchase price 905000
Freight charges 41000
Cost to build special platforms and wiring 21000
Cost of trial runs 7900
Total cost $ 974900
Land Improvements
Trees, plants, and other landscaping 54000
Installation of sprinkler system 5900
Total cost $ 59900

Fork Lifts: $25000 + ($79000 x 0.94340) = $25000 + $74528.60 = $99528.60 = $99529

PV factor for n=1, i=6%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2017. Costs incurred during this period are listed below: Demolition of old building $3300 Architect's fees for new building $13578 Legal fees for title investigation of land $1649 Property taxes on land for period beginning March 1, 2016 $2084 Construction costs $552822 Interest on construction...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 35,000 Legal fees for drawing the contract 9,500 Pro-rated property taxes for the period after acquisition 55,000 State transfer fees 5,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.6 and $1.2 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 26,000 Legal fees for drawing the contract 5,000 Pro-rated property taxes for the period after acquisition 46,000 State transfer fees 5,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent...
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down...
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,200,000. An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000. (compute cost...
Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear...
Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear down two buildings on the land, and the salvage from these old buildings was sold for $1,350. Legal fees of $870 were paid for title investigation and making the purchase. Architect's fees were $10,300. Liability insurance during construction cost $650. Excavation costs were $2,610. A contractor was paid $600,000 to construct the new building. An assessment made by the city for pavement was $1,600....
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down...
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down two buildings on the land. Salvage was sold for $8400. Legal fees of $5480 were paid for title investigation and making the purchase. Architect's fees were $47000. Title insurance cost $3700, and liability insurance during construction cost $4000. Excavation cost $15800. The contractor was paid $4200000. An assessment made by the city for pavement was $9800. Interest costs during construction were $252000. The cost...