Rio Manufacturing Company uses a job order cost system. At the beginning of February, Rio only had one job in process, Job #594. The direct costs assigned to this job at that time were P800 of materials and P650 of labor. Job #594 was finished during February incurring additional direct costs of P120 for materials and P370 for labor. Job #595 was started and finished during February. The direct costs assigned to this job were P310 for materials and P190 for labor. Job #596 was started during February but was not finished by the end of the month. The direct costs assigned to this job were P740 for materials and P300 for labor. Rio applies manufacturing overhead to its products at a rate of 200% of direct labor cost. What is Rio's cost of goods manufactured for February?
1] | The cost of jobs are calculated in the table below: | |||
Job 594 | Job 595 | Job 596 | ||
Beginning WIP inventory cost: | ||||
Materials | 800 | 0 | 0 | |
Labor | 650 | 0 | 0 | |
Overhead assigned | 1300 | 0 | 0 | |
Total | 2750 | |||
Costs incurred during the month: | ||||
Materials | 120 | 310 | 740 | |
Labor | 370 | 190 | 300 | |
Overhead assigned | 740 | 380 | 600 | |
Total costs during the month | 1230 | 880 | 1640 | |
Total costs todate | 3980 | 880 | 1640 | |
2] | Status of completion | Completed | Completed | In progress |
3] | Cost of goods manufactured during february = Cost Job 594+Cost of Job 595 = 3980+880 = | 4860 |