Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:
Machine-hours required to support estimated production | 159,000 | |
Fixed manufacturing overhead cost | $ | 651,000 |
Variable manufacturing overhead cost per machine-hour | $ | 4.90 |
Required:
1. Compute the plantwide predetermined overhead rate.
2. During the year, Job 400 was started and completed. The following information was available with respect to this job:
Direct materials | $ | 310 |
Direct labor cost | $ | 290 |
Machine-hours used | 33 | |
Compute the total manufacturing cost assigned to Job 400.
3. If Job 400 includes 60 units, what is the unit product cost for this job?
4. If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?
Required:
Compute the total manufacturing cost assigned to Job 400. (Round your intermediate calculations to 2 decimal places and your final answer to the nearest dollar amount.)
|
If Job 400 includes 60 units, what is the unit product cost for this job? (Round your intermediate calculations and final answer to the nearest whole dollar.)
|
If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? (Round your intermediate calculations and final answer to the nearest whole dollar.)
|