Question

Gibbs Manufacturing Co. purchased a piece of land to build a new factory. The factory building...

Gibbs Manufacturing Co. purchased a piece of land to build a new factory. The factory building was completed on 8/1/2012. Below is a list of costs incurred with the respective dates.

5 Gibbs Manufacturing Co. purchased a piece of land to build a new factory. The factory building was completed on
8/1/2012. Below is a list of costs incurred with the respective dates.
Date Item Amount
1/31/2012 Land and an old dilapidated building $   240,000
2/28/2012 Cost of removing old building          4,000
4/1/2012 Legal fees (see below)          3,500
5/1/2012 Fire insurance premium payment (see below)          5,400
5/1/2012 Partial payment of new bu ilding construction      170,000
8/1/2012 Final payment on building construction      170,000
8/1/2012 General expenses (see below)        30,000
12/31/2012 Asset write-up        75,000
$   697,900
Additional information:
a) To acquire the land and building on 1/31/12, the company paid $240,000
cash.
b) When the old building was removed, Gibbs paid Kwik Demolition Co.
$4,000, but also received $1,500 from the sale of salvaged material.
c) Legal fees covered the following:
Examination of title covering purchase of land $      2,000
Legal work in connection with the building construction          1,500
$      3,500
d) The fire insurance premium covered premiums for a three-year term
beginning, May 1, 2012.
e) General expenses covered the following for the period 1/2/12 to 8/1/12.
CEO's salary $    20,000
Plant superintendent covering supervision of new building        10,000
$    30,000
f) Because of the rising land costs, the president was sure that the land
was worth at least $75,000 more than what it cost the company.
Instructions
Determine the proper balances as of 12/31/12 for a separate land account and a separate buildings account.

Homework Answers

Answer #1
Land Building
Cost of land and dilapidated building 240000
Cost of removing building 4000
Sale proceeds of salvaged material -1500
Legal fees for title covering purchase of land 2000
Legal fees in connection with building construction 1500
Fire insurance premium ($5400 x 3/36) 450
Partial payment for new building construction 170000
Final payment for new building construction 170000
Plant superintendent covering supervision of new building 10000
Proper balances as of 12/31/12 244500 351950
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Gibbs Manufacturing Co. was incorporated on 1/2/12 but was unable to begin manufacturing activities until 8/1/12...
Gibbs Manufacturing Co. was incorporated on 1/2/12 but was unable to begin manufacturing activities until 8/1/12 because new factory facilities were not completed until that date. The Land and Buildings account at 12/31/12 per the books was as follows: Date                                 Item                                                                              Amount 1/31/12            Land and dilapidated building                                                          $200,000 2/28/12            Cost of removing building                                                                      4,000 4/1/12              Legal fees                                                                                              6,000 5/1/12              Fire insurance premium payment                                                          5,400 5/1/12              Special tax assessment for streets                                                       4,500 5/1/12              Partial payment of new building construction                                    170,000...
Gibbs Manufacturing Co. was incorporated on 1/2/17 but was unable to begin manufacturing activities until 8/1/20...
Gibbs Manufacturing Co. was incorporated on 1/2/17 but was unable to begin manufacturing activities until 8/1/20 because new factory facilities were not completed until that date. The Land and Buildings account at 12/31/20 per the books was as follows: Date   Item Amount 1/31/20 Land and dilapidated building $172,000 2/28/20 Cost of removing building 3,440 4/1/20 Legal fees 5,160 5/1/20 Fire insurance premium payment 4,644 5/1/20 Special tax assessment for streets 3,870 5/1/20 Partial payment of new building construction 180,600 8/1/20...
Gibbs Manufacturing Co. was incorporated on 1/2/19 but was unable to begin manufacturing activities until 8/1/17...
Gibbs Manufacturing Co. was incorporated on 1/2/19 but was unable to begin manufacturing activities until 8/1/17 because new factory facilities were not completed until that date. The Land and Buildings account at 12/31/19 per the books was as follows: Date Item Amount 1/31/19 Land and dilapidated building $200,000 2/28/19 Cost of removing building 4,000 4/1/19 Legal fees 6,000 5/1/19 Fire insurance premium payment   5,440 5/1/19 Special tax assessment for streets 4,500 5/1/19 Partial payment of new building construction 190,000 8/1/19...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $ 62,160 to raze the old buildings and sold salvaged lumber and brick for $ 9,324. Legal fees of $ 2,738 were paid for title investigation and drawing the purchase contract. Sage paid $ 3,256 to an engineering firm for a land survey, and $ 100,640 for drawing...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down...
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,200,000. An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000. (compute cost...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2017. Costs incurred during this period are listed below: Demolition of old building $3300 Architect's fees for new building $13578 Legal fees for title investigation of land $1649 Property taxes on land for period beginning March 1, 2016 $2084 Construction costs $552822 Interest on construction...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT