Question

You got a contract to produce 1000 widgets for the US government. Your initial budget indicated...

You got a contract to produce 1000 widgets for the US government. Your initial budget indicated you would produce 200 widgets a week at a cost of $10/widget. You are required to use the Earned Value Method for progress reports. After 1 week you produced 250 widgets at an actual cost of $2300. What Cost Variance, Schedule Variance and Estimate at Completion will you report?

Homework Answers

Answer #1

Actual cost = $2300

Earned value (EV) = 250 * $10 = $2500

Planned value (PV) = 200*10= $2000

SV = EV – PV = 2500 - 2000 = $500

CV = EV - AC = 2500 - 2300 = $200

SPI = EV/PV = 2500 / 2000 = 1.25

CPI = EV / AC = 2500/2300 = 1.09

There are three different methods to arrive at Estimate at completion

Method 1 - If CPI would remain same, (Budget at Completion) / (Cost Performance Index)

EAC = (1000 * 10) / 1.09 = 9174

Method 2 - If the deviation in week 1 was one off case

EAC = Budget at completion + Actual cost - EV = 10000 + 2300 - 2500 = $9800

Method 3 - If all the parameters of Cost and Schedule will continue for coming weeks

EAC = AC + (BAC – EV) / (CPI * SPI) = 2300 + (10000 - 2500) / (1.09*1.25) = $7804.5

We should report EAC of method 2 as productivity in Week 1 could be one off case and project will continue as normal for coming weeks.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your project has a total budget of $10,000,000. At the end of week 26 of your...
Your project has a total budget of $10,000,000. At the end of week 26 of your project, you have the following values: Planned Value: $1,000,000 Earned Value: $750,000 Actual Cost: $1,250,000 Questions: What is your schedule variance? Is your project ahead of or behind schedule? What is your cost variance? Is your project over budget or under budget? Provide two estimates of the cost at completion for your project. Be sure to show your calculations.
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...