Direct Labor Variances
The following data relate to labor cost for production of 4,000 cellular telephones:
Actual: | 2,720 hrs. at $15.6 | |
Standard: | 2,680 hrs. at $15.8 |
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Rate variance | $ | |
Time variance | $ | |
Total direct labor cost variance | $ |
b. The employees may have been less-experienced or poorly trained, thereby resulting in a labor rate than planned. The lower level of experience or training may have resulted in efficient performance. Thus, the actual time required was than standard.