Question

1. Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company...

1.

Factory Overhead Rates, Entries, and Account Balance

Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows:

Factory 1 Factory 2
Estimated factory overhead cost for fiscal
year beginning March 1 $748,020 $1,006,200
Estimated direct labor hours for year 12,900
Estimated machine hours for year 17,810
Actual factory overhead costs for March $59,840 $86,860
Actual direct labor hours for March 1,160
Actual machine hours for March 1,390

a. Determine the factory overhead rate for Factory 1.
$ per machine hour

b. Determine the factory overhead rate for Factory 2.
$ per direct labor hour

c. Journalize the entries to apply factory overhead to production in each factory for March.

Factory 1
Factory 2

d. Determine the balances of the factory overhead accounts for each factory as of March 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.

Factory 1 $
Factory 2 $

2.

Entries for Direct Labor and Factory Overhead

Townsend Industries Inc. manufactures recreational vehicles. Townsend uses a job order cost system. The time tickets from November jobs are summarized as follows:

Job 201 $3,620
Job 202 1,810
Job 203 1,430
Job 204 2,660
Factory supervision 1,240

Factory overhead is applied to jobs on the basis of a predetermined overhead rate of $30 per direct labor hour. The direct labor rate is $14 per hour.

If required, round final answers to the nearest dollar.

a. Journalize the entry to record the factory labor costs. If an amount box does not require an entry, leave it blank.

b. Journalize the entry to apply factory overhead to production for November.

Homework Answers

Answer #1
1
a
Factory overhead rate for Factory 1 42 per machine hour =748020/17810
b
Factory overhead rate for Factory 2 78 per direct labor hour =1006200/12900
c
Factory 1 :
Work in Process 58380 =1390*42
      Factory overhead 58380
Factory 2 :
Work in Process 90480 =1160*78
      Factory overhead 90480
d
Factory 1 1460 Debit   Underapplied =59840-58380
Factory 2 3620 Credit   Overapplied =90480-86860
2
Work in Process 9520 =3620+1810+1430+2660
Factory overhead 1240
       Wages payable 10760
Work in Process 20400 =(9520/14)*30
     Factory overhead 20400
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $661,080 $897,600 Estimated direct labor hours for year 13,600 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $348,200 $591,600 Estimated direct labor hours for year 8,700 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $632,970 $506,300 Estimated direct labor hours for year 8,300 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $632,970 $506,300 Estimated direct labor hours for year 8,300 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $676,900 $676,500 Estimated direct labor hours for year 12,300 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $665,260 $1,020,000 Estimated direct labor hours for year 15,000 Estimated machine hours for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $498,200 $768,000 Estimated direct labor hours for year 12,000 Estimated machine hours for year 24,910 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $685,980 $672,000 Estimated direct labor hours for year 10,500 Estimated machine hours for year 18,540 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $580,500 $540,000 Estimated direct labor hours for year 9,000 Estimated machine hours for year 23,220 Actual factory overhead costs for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $675,000 $735,300 Estimated direct labor hours for year 12,900 Estimated machine hours for...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT