Trois Elles Corporation recently prepared a manufacturing cost budget for an output of 58,000 units, as follows:
Direct materials | $116,000 |
Direct labor | 58,000 |
Variable overhead | 87,000 |
Fixed overhead | 116,000 |
Actual units produced amounted to 68,000. Actual costs incurred
were: direct materials, $117,000; direct labor, $68,000; variable
overhead, $116,000; and fixed overhead, $113,000. If Trois Elles
evaluated performance by the use of a flexible budget, a
performance report would reveal a total variance of (Round
intermediate calculations to 2 decimals and the final answer to the
nearest dollar amount.):
$8,000 favorable.
$5,000 favorable.
$44,000 unfavorable.
$37,000 unfavorable.
None of these.
Zin, Inc. is planning its cash needs for an upcoming period when 96,000 machine hours are expected to be worked. Activity may drop as low as 89,000 hours if some overdue equipment maintenance procedures are performed; on the other hand, activity could jump to 105,000 hours if one of Zin's major competitors likely goes bankrupt. A flexible cash budget to determine cash needs would best be based on:
105,000 hours.
96,000 hours.
89,000 hours.
89,000 hours and 105,000 hours.
89,000 hours, 96,000 hours, and 105,000 hours.
Gourmet Restaurants has the following flexible-budget formula:
Y = $14 PH + $540,000 where PH is defined as process
hours.
What is Gourmet's budgeted total cost if its process hours equal
27,000?
$378,000.
$540,000.
$918,000.
$1,458,000.
Answer cannot be determined from the information provided.
Ans 1 | |||||
Static S | Flexible F | Actual A | Varince | ||
units | 58000 | 68000 | 68000 | ||
Direct material | 136000 | 117000 | 19000 | F | |
116000/58000*68000 | |||||
Direct Labor | 68000 | 68000 | 0 | None | |
58000/58000*68000 | |||||
Variable overhead | 102000 | 116000 | 14000 | U | |
87000/58000*68000 | |||||
Fixed Overhead | 116000 | 116000 | 113000 | 3000 | F |
490000 | 482000 | 8000 | F | ||
option A $8000 | |||||
ans 2 | |||||
96000 hours as it is expected hours | |||||
ans 3 | |||||
Y=14PH+540000 | |||||
Y=(14*27000)+540000 | 918000 | ||||
Option C $918000 |