Question

A contracting firm anticipates that it will incur costs in excess of the contract price on...

A contracting firm anticipates that it will incur costs in excess of the contract price on a particular contract. The firm has completed two years of work but the contract is only 60% complete. What portion of the entire anticipated loss is recognized as of the end of the second year? Which section of the authoritative literature best describes this situation and provides the appropriate guidance?

Homework Answers

Answer #1

As you can observe, the firm is anticipating a loss. And also 60% of the contract is already completed.

As of the end the second year, the loss to the extent of 60% should be recognised because the project is already completed to that extent and the loss is also already incurred. And to the remaining 40% should create a contingent liability, because this loss is not yet incurred but is anticipated that it will definitely be incurred.

This is as per IFRS 37. That is the authoritative literature that best describes the above situation is IFRS 37 issued by IASB.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Wayne Schuller managed a warehouse in Minnetonka, Minnesota. His major concern was the number of workers...
Wayne Schuller managed a warehouse in Minnetonka, Minnesota. His major concern was the number of workers to assign to his single unloading dock. After he began contracting with motor carriers for deliveries, he found that they were assessing him stiff penalties if their trucks had to wait to be unloaded. Wayne started adding larger crews at the unloading dock, but often they seemed idle because there were no trucks to unload. Wayne recalled from college that queueing theory might be...
During the trial, lawyers for the accused said that the men believed that the accounting decisions...
During the trial, lawyers for the accused said that the men believed that the accounting decisions they made were appropriate at the time, and that the accounting treatment was approved by Nortel’s auditors from Deloitte & Touche. Judge Marrocco accepted these arguments. Marrocco added he was “not satisfied beyond a reasonable doubt” that the trio (i.e., Dunn, Beatty, and Gollogly) had “deliberately misrepresented” financial results. Given the facts of the case, do you believe Judge Marrocco’s decision was justified? Explain....
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be transmitted, photocopied, digitized, or otherwise reproduced in any form or by any means without the permission of the copyright holder. Reproduction...
QUESTION: Why do governments typically take an unsupportive stance on countertrade arrangements? Article Below: The Bell...
QUESTION: Why do governments typically take an unsupportive stance on countertrade arrangements? Article Below: The Bell Boeing V-22 Program, a strategic alliance between Bell Helicopter, a Textron Company, and the Boeing Company,1,2 announced the V-22 Osprey tiltrotor will be featured at the Dubai International Air Show in the United Arab Emirates (UAE) from November 13 to 17, 2011. The Air Show, held biennially, is organized in cooperation with the government of Dubai, the Department of Civil Aviation, and Dubai International...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT