Using the provided budgeted information for production of 10,000 and 15,000 units, prepare a flexible budget for 17,000 units.
Production 10,000 units 15,000 units 17,000 units
Expense A $15,000 $22,500 ?
Expense B $21,000 $21,000 ?
Expense C $43,000 $43,000 ?
In the solution Expense B and Expense C are fixed expenses and
Expense A is Variable Expense i.e it change with change in Units
produced .
As units produced increased Expense A increased but Expense B and C
remain same