Question

Budgeted production 26,000 units Actual production 27,500 units Labor:   Standard hourly labor rate $22 per hour...

Budgeted production

26,000 units

Actual production

27,500 units

Labor:

  Standard hourly labor rate

$22 per hour

  Standard hours allowed per completed unit

6.6

  Actual labor hours worked

183,000

  Actual total labor costs

$4,020,000

What is the labor price variance?

5,490 unfavorable

5,490 favorable

33,000 favorable

33,000 unfavorable

Homework Answers

Answer #1
BUDGETED (26000 UNIT) STANDARD (27500 UNITS) ACTUAL (27500 UNITS)
HOURS RATE AMOUNT HOURS RATE AMOUNT HOURS RATE AMOUNT
171600 22 3775200 181500 22 3993000 183000 21.96721 4020000
(26000*6.6) (27500*6.6)
Labour price variance = (Standard Hours - Actual Hours)* Standard rate
(181500 - 183000)*22
33000 Unfavourable

If the option is- None of the above then that must be selected.

Above answer is for Labour Efficiency variance. Since no option is matching, I have to find out Labour Efficiency rate in place of Labour Price Variance.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 994 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $12.86 per hour. The direct labor rate variance is a.$6,881.72 unfavorable b.$6,881.72 favorable c.$5,577.18 unfavorable d.$5,577.18 favorable 21. Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.08 per hour. Original...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.61 Actual Costs Direct materials 2,600 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is $426 favorable $426 unfavorable $1,066 favorable $1,066 unfavorable Q2: The standard costs and actual costs for direct materials for the manufacture of 2,650 actual units of...
Williams Corporation reports the following direct labor information for November: Standard rate $ 34.00 per hour...
Williams Corporation reports the following direct labor information for November: Standard rate $ 34.00 per hour Actual rate paid $ 34.90 per hour Standard hours allowed for actual production 44,700 hours Labor efficiency variance $ 234,600 F Required: Based on these data, what was the number of actual hours worked and what was the labor price variance? (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select...
Use this information for Stringer Company to answer the question that follow. The following data are...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:...
17 - Use this information for Harry Company to answer the question that follow. The following...
17 - Use this information for Harry Company to answer the question that follow. The following data are given for Harry Company: Budgeted production 1,069 units Actual production   909 units Materials:     Standard price per ounce $1.85     Standard ounces per completed unit 12     Actual ounces purchased and used in production 11,235     Actual price paid for materials $23,032 Labor:     Standard hourly labor rate $14.44 per hour     Standard hours allowed per completed unit 4.2     Actual labor hours worked 4,681     Actual total labor costs...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct labor variance $8,600 Unfavorable . Direct labor rate variance $4,000 Unfavorable . Standard hours allowed per unit produced 2 hours Required: Find the following unknowns. a. Direct labor efficiency variance b. Standard rate per direct labor hour c. Actual quantity produced
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct...
Actual quantity of direct labor 5,000 hours Actual direct labor rate $10 per hour Total direct labor variance $8,600 Unfavorable . Direct labor rate variance $4,000 Unfavorable . Standard hours allowed per unit produced 2 hours Required: Find the following unknowns. Actual quantity produced
Lamp Company produces lamps that require 2 standard hours per unit at a standard hourly rate...
Lamp Company produces lamps that require 2 standard hours per unit at a standard hourly rate of $20.60 per hour. Production of 6,700 units required 13,130 hours at an hourly rate of $20.00 per hour. What is the direct labor (a) rate variance, (b) time variance, and (c) total cost variance? Enter favorable variances as negative numbers. a. Direct labor rate variance $ b. Direct labor time variance $ c. Total direct labor cost variance Determine also if favorable or...
We know the following totals: Actual hours x Actual rate per hour = $125000 Standard rate...
We know the following totals: Actual hours x Actual rate per hour = $125000 Standard rate per hour x Hours that SHOULD have been used for the actual production achieved = $121000 Standard rate per hour x actual hours = $149000 What is the TOTAL Labor Variance? (Note, I just want the AMOUNT, not whether it was favorable or unfavorable.)
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT