Question

Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following...

Stage 2 ABC for Manufacturing:
Reassigning Costs to Cost Objectives
Regal Products has developed the following activity cost information for its manufacturing activities:

Activity Activity cost
Machine setup $60.00 per batch
Movement 15.00 per batch move
0.10 per pound
Drilling 5.00 per hole
Welding 2.00 per inch
Shaping 25.00 per hour
Assembly 19.00 per hour
Inspection 2.00 per unit

Filling an order for a batch of 50 fireplace inserts (each insert weighing 150 pounds) required the following:

  • Three batch moves
  • Two sets of inspections
  • Drilling five holes in each unit
  • Completing 50 inches of welds on each unit
  • Thirty minutes of shaping for each unit
  • One hour of assembly per unit

Determine the activity cost of converting the raw materials into 50 fireplace inserts.
$Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $70.00 per batch Movement 20.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 8.00 per inch Shaping 29.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 150 pounds each required the following: • Three batch moves...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: • Four batch moves...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: • Four batch moves...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities: Budgeted Activity Cost Activity Cost Driver at Practical Capacity Purchasing and materials handling $675,000 900,000 kilograms Setup 700,000 1,120 setups Machine operations 954,000 12,000 hours First unit inspection 50,000 1,000 batches Packaging 250,000 312,500 units Actual 2016 production information is as follows: Standard Product A Standard Product B Specialty Products Units 150,000 100,000 50,000 Batches 100 80 600 Setups*...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $25 per machine hour Assembly $32 per direct labor hour Setup $87 per setup Inspecting $15 per inspection Production scheduling $14 per production order Purchasing $5 per...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $344,760 Machine hours Assembly 231,200 Direct labor hours Inspecting 38,080 Number of inspections Setup 33,360 Number of setups Materials handling 43,680 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $250,900 Machine hours Assembly 154,000 Direct labor hours Inspecting 26,620 Number of inspections Setup 43,120 Number of setups Materials handling 45,120 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $325,710 Machine hours Assembly 202,500 Direct labor hours Inspecting 33,150 Number of inspections Setup 36,480 Number of setups Materials handling 42,750 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
ABC uses activity based costing where overhead from three different production departments are allocated to products...
ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity                                     Driver                                        Activity Rate                                         Product A              Product B Cutting                                     Machine Hours                                     $2.00 per machine hour                                2,000 hours        3,000 hours Assembly              Assembly Hours                 $.50 per assembly hour                                   3,000 hours        5,000 hours Painting                 Gallons of Paint                                   $5.00 per gallon                                  1,500 gallons     1,300 gallons Raw materials are directly followed to each product and the amount of raw materials used for...
ABC uses activity based costing where overhead from three different production departments are allocated to products...
ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity - Driver - Activity Rate - Product A - Product B Cutting - Machine Hours - $2.00 per machine hour - 2,000 hours - 3,000 hours Assembly - Assembly Hours - $.50 per assembly hour - 3,000 hours - 5,000 hours Painting - Gallons of Paint - $5.00 per gallon - 1,500 gallons - 1,300 gallons Raw materials are directly followed...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT