Question

Amben ltd a furniture production company has three production centers: Machine shop X, machine shop Y...

Amben ltd a furniture production company has three production centers: Machine shop X, machine shop Y and one assembly center. From the data below compute the overhead absorption rates for each center

Production center        Overhead        machine hours             labour hours

Machine shop X          $4,300,000     1,000,000                    500,000

Machine shop Y          $3,800,000     500,000                       1,000,000

Assembly                    $3,600,000     800,000                       1,200,000

Two products A and B were manufactured during the period:

Product A (100 units)                                                 $

Direct costs (100 units X $100)                                  10,000

Overheads:

            Machine center A. (5 machine hours)

            Machine center B.   (10 machine hours)

            Assembly                (10 direct labour hours)

Product B (200)

Direct costs (200 units $200)                                      40,000

Overheads:

            Machine center A. (10 machine hours)

            Machine center B.   (20 machine hours)

            Assembly                (20 direct labour hours)

Required:

Compute the total cost for each product

Compute the cost per unit for each product.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
11. The Accountant for APC Manufacturing Pty Ltd, a manufacturer of Sports Wear has accumulated the...
11. The Accountant for APC Manufacturing Pty Ltd, a manufacturer of Sports Wear has accumulated the following information related to the anticipated overhead costs for the coming year. factory office stores assembly finishing total dept overhead $60,000 $15,000 $80,000 $45,000 $200,000 departmental information plant value $15,000 $35,000 $270,000 $80,000 $400,000 floor space(m2) 100 200 500 300 1,100 requisitions 60 40 100 No. of employees 22 55 33 110 direct labour hours 2,000 6,000 8,000 machine hours 12,650 2,350 15,000 The...
Duck Company makes three products (X, Y, & Z) with the following characteristics: Products X Y...
Duck Company makes three products (X, Y, & Z) with the following characteristics: Products X Y Z Selling price per unit $ 10 $ 15 $ 20 Variable cost per unit $ 6 $ 10 $ 10 Machine hours per unit 2 4 10 The company has a capacity of 2,000 machine hours, but there is virtually unlimited demand for each product. In order to maximize total contribution margin, how many units of each product should the company produce? Multiple...
Part 1 ABC uses activity based costing where overhead from three different production departments are allocated...
Part 1 ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity                 Driver - Activity Rate - Product A - Product B Cutting Machine Hours - $2.00 per machine hour - 2,000 hours - 3,000 hours Assembly            Assembly Hours - $.50 per assembly hour - 3,000 hours - 5,000 hours Painting                Gallons of Paint - $5.00 per gallon - 1,500 gallons - 1,300 gallons Raw materials are directly followed to...
Mathematical                         Financial Annual Production in Units            
Mathematical                         Financial Annual Production in Units                                            50 000 100 000 Direct Material Costs 150 000 300 000 Direct Manufacturing Labour Cost 50 000 100 000 Direct manufacturing labour hours 2, 500 5 000 Machine Hours 25 000 50 000 Number of Production runs                                             50 50 Inspection hours 1 000 500 Total Manufacturing Overhead Costs are as follows: Total                                                                       Machining costs 375 000                                                                       Setup Costs 120 000                                                                       Inspection costs 105 000 Instruction: 1. Choose a...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool       Activity Measure        Estimated Overhead Cost      Expected Activity Machining             Machine-hours        $ 200,000                       10,000 MHs Machine setups Number...
Calculate the product cost and profitability of each of Wayco Leisure’s three types of product using...
Calculate the product cost and profitability of each of Wayco Leisure’s three types of product using each of the following methods to attribute overheads: (I) The existing methods based upon labour hours. information. Direct labour $20 per hour Annual Output (Units) Annual Direct labour hours Selling price ($ per unit) Raw material cost ($ per unit) Getaway 2000 50,000 4,000 400 Relax 1600 55,000 6,000 600 Unwind 400 20,000 8,000 900 The three cost drivers that generate overheads are: Deliveries...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct labour hours at a standard rate of $11 per hour. During the last year, MNO assembly line workers worked a total of 5,000 hours at a cost of $50,000 to MNO. Also last year, MNO manufactured 3,000 units of product. What was the company's direct labour rate variance for the year? 2) MNO produces a single product. The standard production requirement for each unit...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
ABC uses activity based costing where overhead from three different production departments are allocated to products...
ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity                                     Driver                                        Activity Rate                                         Product A              Product B Cutting                                     Machine Hours                                     $2.00 per machine hour                                2,000 hours        3,000 hours Assembly              Assembly Hours                 $.50 per assembly hour                                   3,000 hours        5,000 hours Painting                 Gallons of Paint                                   $5.00 per gallon                                  1,500 gallons     1,300 gallons Raw materials are directly followed to each product and the amount of raw materials used for...
ABC uses activity based costing where overhead from three different production departments are allocated to products...
ABC uses activity based costing where overhead from three different production departments are allocated to products as follows: Activity - Driver - Activity Rate - Product A - Product B Cutting - Machine Hours - $2.00 per machine hour - 2,000 hours - 3,000 hours Assembly - Assembly Hours - $.50 per assembly hour - 3,000 hours - 5,000 hours Painting - Gallons of Paint - $5.00 per gallon - 1,500 gallons - 1,300 gallons Raw materials are directly followed...