Which of the following is NOT a characteristic of a project?
A. |
They are unique. |
|
B. |
They are routine. |
|
C. |
They have specific due date. |
|
D. |
They have a specific deliverable. |
|
E. |
They have a purpose. |
Which of the following can be included in a weighted scoring model for prioritization and selection of projects?
A. |
potential profitability of the project |
|
B. |
potential impact on the firm’s competitive position |
|
C. |
the organization’s ability to market the output of a project |
|
D. |
All of the above can be included |
|
E. |
only answers 1 and 2 above |
Which of the following would be considered “projects” based on the definition from text and lecture?
A. |
the design and development of a new product |
|
B. |
gathering and entering employment data for a Bureau of Labor Statistics quarterly report |
|
C. |
producing a car on an automobile assembly line |
|
D. |
answers 1 and 2 above |
|
E. |
answers 1, 2, and 3 above |
Answer: Option B. They are routine.
Projects are characterized to be non-routine and unique, having a specific purpose, deliverable, and due date by which to be completed. Hence, option B. is the correct answer.
Answer: Option D. All of the above can be included.
All the three items mentioned may be included as the criteria for the prioritization and selection of a project and hence, option D. is the correct answer.
Answer: Option D. answers 1 and 2 above
Producing a car on an automobile assembly line is of a routine nature and not a project while designing and developing a new product and gathering and entering data for the Bureau meet various characteristics of a project and hence option D. is the correct answer.