Question

Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...

Two-Stage ABC for Manufacturing with Variances
Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities:

Budgeted Activity Cost

Activity Cost Driver at Practical Capacity

Purchasing and materials handling

$675,000

900,000 kilograms
Setup

700,000

1,120 setups

Machine operations

954,000

12,000 hours

First unit inspection

50,000

1,000 batches

Packaging

250,000

312,500 units

Actual 2016 production information is as follows:

Standard Product A

Standard Product B

Specialty Products

Units 150,000 100,000 50,000
Batches 100 80 600
Setups* 300 160 900
Machine operations (hours) 6,000 3,000 2,000
Kilograms of raw materials 400,000 300,000 200,000
Direct materials costs $900,000 $600,000 $820,000

*Some products require setups on two or more machines.



a. Determine the unit cost of each product for Montreat Manufacturing.
Round rates to two decimal places.
Activity-based overhead rates:

Purchasing & materials handling $Answer
Setup $Answer
Machine operations $Answer
First unit inspection $Answer
Packaging $Answer

Use rounded overhead rates calculated above for calculations below. Round cost answers to the nearest whole number, when needed.
Round cost per unit to two decimal places.

Standard Product A Standard Product B Specialty Products
Direct material $Answer $Answer $Answer
Overhead cost
Purchasing & handling Answer Answer Answer
Setup Answer Answer Answer
Machine operations Answer Answer Answer
First unit inspection Answer Answer Answer
Packaging Answer Answer Answer
Total costs $Answer $Answer $Answer
Units Answer Answer Answer
Cost per unit $Answer $Answer $Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined the...
Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity cost pool Activity cost Activity cost driver Machine setup $600,000 12,000 setup hours Material handling 60,000 2,000 tons of materials Machine operation 500,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts: C23 Cams U2 Shafts Units produced 500 100...
Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined the...
Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity cost pool Activity cost Activity cost driver Machine setup $600,000 12,000 setup hours Material handling 180,000 2,000 tons of materials Machine operation 500,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts: C23 Cams U2 Shafts Units produced 500 200...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity cost pool Activity cost Activity cost driver Machine setup $950,000 2,500 setup hours Material handling 520,000 5,000 material moves Machine operation 200,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 30,000 20,000 Direct labor hours 500 250 Machine...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $70.00 per batch Movement 20.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 8.00 per inch Shaping 29.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 150 pounds each required the following: • Three batch moves...
Activity-Based Determining the cost of a product, which consist of direct materials, direct labor, and factory...
Activity-Based Determining the cost of a product, which consist of direct materials, direct labor, and factory overhead.Product Costing Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Cost Pool Production $259,200 Changing the characteristics of a machine...
Sheridan Industries has three activity cost pools and two products. It estimates production 2,000 units of...
Sheridan Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Sheridan accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: • Four batch moves...
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following...
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following activity cost information for its manufacturing activities: Activity Activity cost Machine setup $60.00 per batch Movement 15.00 per batch move 0.10 per pound Drilling 5.00 per hole Welding 2.00 per inch Shaping 25.00 per hour Assembly 19.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts (each insert weighing 150 pounds) required the following: Three batch moves...
10. Vertex Tires manufactures tires for dune buggies and has two different products, nubby tires and...
10. Vertex Tires manufactures tires for dune buggies and has two different products, nubby tires and smooth tires. The company produces 5,000 nubby tires and 10,000 smooth tires each year and incurs $167,000 of overhead costs. The following information is available:      Activity       Total Cost         Cost Driver   Materials handling $60,000       Number of requisitions Machine setups      50,000       Number of setups Quality inspections 57,000       Number of inspections For the nubby tires, the company has 400 requisitions, 200 setups, and 200...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours 34,000...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT