San Juan, Inc. is considering two alternatives: A and B. The
costs associated with the alternatives are listed below:
Alternative A | Alternative B | ||||||
Material costs | $ | 35,000 | $ | 60,000 | |||
Processing costs | 40,000 | 60,000 | |||||
Building costs | 13,100 | 30,000 | |||||
Equipment rental | 20,100 | 20,100 | |||||
If only the differential costs of the two decisions are considered,
the total cost of Alternative B is
$139,150.
$61,900.
$108,200.
$170,100.
Costs Alternative A:
Material costs $ 35,000
Processing costs 40,000
Building costs 13,100
Total= $88100
---------------------------------------------------------
Costs Alternative B:
Material costs $ 60,000
Processing costs $60,00
Building costs $30,000
Total= $150,000
----------------------------------------------------------------
Total differential cost = 150000 - 88100 = $61900
----------------------------------------------------------------
Explanation:
The cost which is same in both the alternatives, i.e Equipment rental, will not be considered in calculating the cost.