Question

Morris Manufacturing Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two...

Morris Manufacturing Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two line departments, X and Y. The cost driver in MD is service hours. The cost driver in PD is number of employees. Plan data for the departments, including service hours used by each department, is shown below. Using the direct method, what is plan PD cost assigned to Department Y?
   MD    PD X Y
service hours -- 75   600 300
employees 50   100 150   150
labor hours 125 125   500 250
plan cost (000s) $30 $4.5 $9 $15

Homework Answers

Answer #1

The cost driver in PD is number of employees.

Hence, plan PD cost will be allocated to departments on the basis of number of employees.

Number of employees in department X = 150

Number of employees in department Y = 150

Total number of employees in departments X and Y = Number of employees in department X + Number of employees in department Y

= 150 + 150

= 300

Plan PD cost assigned to Department Y = Plan PD cost x Number of employees in department Y/Total number of employees in departments X and Y

= 4,500 x 150/300

= $2,250

Please ask if you have any query related to the question. Thank you

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Oaks Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two line...
Oaks Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two line departments, P1 and P2. The MD cost driver is service hours. The PD cost driver is number of employees. Plan data, including service hours used by each department, is shown below. What is planned MD cost assigned to P2 using the direct method?    MD PD P1 P2 service hours -- 50 300 150 employees 10 20 90 90 labor hours 50 50 250...
Hanung Corp has two service departments, Maintenance and Personnel. Maintenance Department costs of $300,000 are allocated...
Hanung Corp has two service departments, Maintenance and Personnel. Maintenance Department costs of $300,000 are allocated on the basis of budgeted maintenance-hours. Personnel Department costs of $170,000 are allocated based on the number of employees. The costs of operating departments A and B are $188,000 and $282,000, respectively. Data on budgeted maintenance-hours and number of employees are as follows: Production Support Departments Departments   Maintenance Department Personnel Department A B Budgeted costs $300,000 $170,000 $188,000 $282,000 Budgeted maintenance-hours NA 860 1280...
Jake’s Battery Company has two service departments, Maintenance and Personnel. Maintenance Department costs of $160,000 are...
Jake’s Battery Company has two service departments, Maintenance and Personnel. Maintenance Department costs of $160,000 are allocated on the basis of budgeted maintenance-hours. Personnel Department costs of $40,000 are allocated based on the number of employees. The costs of operating departments A and B are $80,000 and $120,000, respectively. Data on budgeted maintenance-hours and number of employees are as follows: Support Departments Production Departments Maintenance Department Personnel Department A B Budgeted costs $160,000 $40,000 $80,000 $120,000 Budgeted maintenance-hours NA 400...
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing)....
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing). Management has decided to allocate maintenance costs on the basis of machine-hours in each department and personnel costs on the basis of labor-hours worked by the employees in each. The following data appear in the company records for the current period: Maintenance Personnel Printing Developing Machine-hours − 495 594 2,211 Labor-hours 400 − 300 1,300 Department direct costs $ 11,000 $ 23,000 $ 34,000...
Company “ABC” has two service departments. Maintenance and personnel. Maintenance Department cost pf $320,000 are allocated...
Company “ABC” has two service departments. Maintenance and personnel. Maintenance Department cost pf $320,000 are allocated on the basis of budgeted maintenance-hours. Personnel department costs of $80,000 are allocated based on the number of employees. The costs of operating departments A and B are $160,000 and $240,000 respectively. Data on budgeted maintenance-hours and number of employees: Support Departments Production Departments Maintenance Department Personnel Department A B Budgeted costs $320,000 $80,000 $160,000 $240,000 Budg maintenance-hrs NA 800 960 640 Number of...
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing)....
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing). Management has decided to allocate maintenance costs on the basis of machine-hours in each department and personnel costs on the basis of labor-hours worked by the employees in each. The following data appear in the company records for the current period: Maintenance Personnel Printing Developing Machine-hours — 1,700 1,700 5,100 Labor-hours 700 — 700 2,800 Department direct costs $ 2,400 $ 12,400 $ 14,100...
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing)....
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing). Management has decided to allocate maintenance costs on the basis of machine-hours in each department and personnel costs on the basis of labor-hours worked by the employees in each. The following data appear in the company records for the current period: Maintenance Personnel Printing Developing Machine-hours ---- 1,800 1,800 5,400 Labor-hours 650 — 650 2,600 Department direct costs $ 4,000 $ 14,000 $ 15,900...
30. Hanung Corp has two service​ departments, Maintenance and Personnel. Maintenance Department costs of $310,000 are...
30. Hanung Corp has two service​ departments, Maintenance and Personnel. Maintenance Department costs of $310,000 are allocated on the basis of budgeted maintenance−hours. Personnel Department costs of $150,000 are allocated based on the number of employees. The costs of operating departments A and B are $184,000 and $276,000​, respectively. Data on budgeted maintenance−hours and number of employees are as​ follows:                                                                                                                     Support Departments Production Departments Maintenance Department Personnel Department A B Budgeted costs $310,000 $150,000 $184,000 $276,000 Budgeted maintenance−hours NA 880...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $65,000 $33,000 $74,000 Square feet occupied 2,000 3,500 3,000 Number of employees 42 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,030 $114,090 Square feet occupied 2,100 1,400 Number of employees 36 18 Maintenance hours...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $69,000 $45,000 $78,000 Square feet occupied 2,000 3,500 3,000 Number of employees 36 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,040 $122,090 Square feet occupied 2,100 1,400 Number of employees 42 18 Maintenance hours...