When an ACAT I program is required to submit a quarterly selected Acquition Report (SAR)? Select all that apply.
A. Milestone B or Milestone C approval is received during the quarter
B. Program Acquisition Unit Cost is now estimated to exceed the objective value in the program's Current Acquisition Program baseline by more than 15% (program base year dollars)
C. A schedule parameter is now expected to slip more than 3 months, but less than 6 months, than reported in the previous SAR
D. Average Procurement Unit Cost is now estimated to exceed the objective value in the program's ORIGINAL Acquisition Program Baseline by more than 25% (program base year dollars)
(Quarterly SARS are submitted only on an "exception" basis as described below. If required, they cover the quarters ending 31 March, 30 June, and 30 September and must submitted within 45 days after the quarter end date. A quarterly SAR is required if any one of the following applies:
The current estimate includes a 6-month or greater delay, for any schedule parameter, that occurred since the previous SAR.
Milestone B or Milestone C approval occurs within the reportable quarter.
A Nunn-McCurdy cost breach occurs during the reporting quarter.
Answer : Option A