Beavis Construction Company was the low bidder on a construction
project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam for $1,800,000. The project was
begun in 2012 and completed in 2013. Cost and other data are
presented below:
2012
2013
Costs
incurred during the year
$
450,000
$1,100,000
Estimated costs to complete
1,050,000
0
Billings
during the year
400,000
1,400,000
Cash collections during the year
300,000
1,500,000
Assume that Beavis recognizes revenue on this contract over time
according to...
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam for $1,800,000. The project was
begun in 2015 and completed in 2016. Cost and other data are
presented below:
2012
2013
Costs
incurred during the year
$
450,000
$1,100,000
Estimated costs to complete
1,050,000
0
Billings
during the year
400,000
1,400,000
Cash collections during the year
300,000
1,500,000
Assume that Beavis recognizes revenue on this contract over time
according to...
Part A
Two days before the financial year end of 31 December 2019, a
major customer...
Part A
Two days before the financial year end of 31 December 2019, a
major customer requested WT Limited to defer delivering 100,000
units of Product A until 2 January 2020 because the customer’s
warehouse had already been closed for the New Year holidays. The
customer requested WT Limited to issue the invoice for the goods at
the current year end though the goods were delivered on 2 January
2020 and agreed to settle the amount within 30 days after...
McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun in 2017 and
completed in 2018. Cost and other data are presented below:
2017
2018
Costs incurred during the
year
$1,500
$1,300
Estimated costs to
complete
1,200
0
Billings during the
year
1,200
1,300
Cash collections during the
year
1,000
1,500
Compute the amount of revenue and gross profit recognized
during 2017 and 2018.
Assume that McCombs recognizes revenue on this contract over...
On February 1, 2021, Arrow Construction Company entered into a
three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,210,000. During 2021, costs of $2,070,000 were incurred with
estimated costs of $4,070,000 yet to be incurred. Billings of
$2,570,000 were sent, and cash collected was $2,320,000.
In 2022, costs incurred were $2,570,000 with remaining costs
estimated to be $3,705,000. 2022 billings were $2,820,000 and
$2,545,000 cash was collected. The project was completed in 2023
after additional costs of...
Sallys construction. is a construction company and recognizes
revenue, costs, and gross profit at project completion....
Sallys construction. is a construction company and recognizes
revenue, costs, and gross profit at project completion. At the
start of Year 1, Kip enters a contract to build an office building
for $100 million. The project is completed by the end of Year 2.
The following additional information is available for this project
(amounts in millions):
YEAR 1 YEAR 2
Costs incurred during each year
$20 $70
Costs expected in future
$60 0
sallys Year 2 revenue will be:
In 2017, Chicago Construction began work on a three-year
construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year
construction project to build a new performing arts complex (the
"PAC"). Chicago uses the percentage-of-completion method of
accounting. At the end of 2017, the company completed 25% of the
project. The following financial statement information indicates
the results to date for the PAC at the end of 2017:
Actual Cost incurred in
2017
$35 million
Construction in progress (as of
12/31/2017)
$50 million
Accounts Receivable from construction billings (as of...
Revenue Recognition
In 2017, Chicago Construction began work on a three-year
construction project to build a...
Revenue Recognition
In 2017, Chicago Construction began work on a three-year
construction project to build a new performing arts complex (the
"PAC"). Chicago uses the percentage-of-completion method of
accounting. At the end of 2017, the company completed 25% of the
project. The following financial statement information indicates
the results to date for the PAC at the end of 2017:
Actual Cost incurred in 2017 $35 million
Construction in progress (as of
12/31/2017) $50
million
Accounts Receivable from construction billings (as...
In 2013, Thomas Jefferson contracted to build an airplane for
$12,000,000. Data relating to the contract...
In 2013, Thomas Jefferson contracted to build an airplane for
$12,000,000. Data relating to the contract are as follows: ($ in
thousands) 2013 2014 Costs incurred during the year $2,000 $6,000
Estimated costs to complete as of year-end 6,000 - Billings during
the year 6,000 6,000 Cash collections during the year 5,000 7,000
Determine the gross profit that Thomas Jefferson should recognize
in both 2013 and 2014 using the percentage-of-completion
method.
On June 15, 2020, Lion Construction signed a $ 360,000 contract
to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract
to build a small building. Lion estimated that the total cost would
be $ 320,000. Construction started immediately because the required
completion date was August 31, 2021. Lion’s relevant data relating
to this construction project were as follows:
2020
2021
Actual costs incurred $ 120,000 $
204,000
Estimated costs to complete
200,000
-0-
Progress billings
112,000 248,000
Collections 110,000
250,000
Instructions (show all supporting
calculations)
Calculate how much...