Seaton Enterprises used a normal costing system during 2018 with machine hours as the cost drive for applying manufacturing overhead. At the beginning of 2018, manufacturing overhead was budgeted to be $600,000. Seaton also budgeted 8,000 labor hours and 2,000 machine hours to be used during the year. Actual overhead for the year was $610,000. Seven thousand eight hundred labor hours and 2,100 machine hours were actually used during the year. The amount of over applied or under applied manufacturing overhead (indicate the amount and whether it was under or over applied) for 2018 was:
Answer:
Predetermined Overhead Rate = Estimated Manufacturing Overhead /
Estimated Machine Hour
Predetermined Overhead Rate = $600,000 / 2,000
Predetermined Overhead Rate = $300
Actual Overhead = $610,000
Overhead Applied = Machine Hour applied * Predetermined Overhead
Rate
Overhead Applied = 2,100 * $300
Overhead Applied = $630,000
As Overhead applied $630,000 is more than the actual overhead $610,000, the overhead is over-applied by $20,000 ($630,000 - $610,000).
Get Answers For Free
Most questions answered within 1 hours.