Question

During the year, the highest and lowest levels of activity for the Cutler Company were 34,000...

During the year, the highest and lowest levels of activity for the Cutler Company were 34,000 direct machine hours and 24,000 direct machine hours, respectively. If maintenance costs were $240,000 at the 34,000-hour level and $200,000 at the 24,000-hour level, what cost might we expect at an operating level of 28,000 direct machine hours?

Homework Answers

Answer #1
Using High low method
Variable cost per direct machine hour $ 4.00 =(240000-200000)/(34000-24000)
( Change in cost / change in level of activity)
Fixed Costs $ 104,000 =240000-(34000*4)
At operating level of 28,000 direct machine hours
Variable Costs ( 28,000 x 4 )        112,000
Fixed Costs        104,000
Total Costs $ 216,000
At an operating level of 28,000 direct machine hours we might expect cost of $ 216,000.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following selected data were taken from the accounting records of Manitoba Manufacturing Company. The company...
The following selected data were taken from the accounting records of Manitoba Manufacturing Company. The company uses direct-labor hours as its cost driver for overhead costs.   Month Direct-Labor Hours Manufacturing Overhead   January 24,000       $ 750,250   February 23,000       724,000   March 26,000       778,500   April 21,000       685,000   May 28,000       781,500   June 30,000       883,000 June’s costs consisted of machine supplies ($123,000), depreciation ($24,500), and plant maintenance ($735,500). These costs Exhibit the following respective behavior: variable, fixed, and semivariable....
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Question # 7 Dubai Heavy Industries (DHI) is manufacturing company whose total manufacturing overhead costs fluctuate...
Question # 7 Dubai Heavy Industries (DHI) is manufacturing company whose total manufacturing overhead costs fluctuate somewhat from year to year according to the number of machine-hours worked in its production facility. These costs at high and low levels of activity over recent years are given below: Level of Activity Low High Machine-hours 60,000 80,000 Total Manufacturing Overhead Costs $274,000 $312,000 The manufacturing overhead costs above consist of Indirect Materials, Rent, and Maintenance. The company has analyzed these costs at...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours Total Overhead Cost   September 112,800 $ 781,512   October 89,200 $ 662,568   November 157,200 $ 1,005,288   December 165,000 $ 1,044,600 Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:   Utilities (variable) $ 233,704   Supervisory salaries       and depreciation (fixed) 172,000   Maintenance (mixed)      256,864   Total overhead...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Marquis Company estimates that annual manufacturing overhead costs will be $822,600. Estimated annual operating activity bases...
Marquis Company estimates that annual manufacturing overhead costs will be $822,600. Estimated annual operating activity bases are direct labor cost $457,000, direct labor hours 45,700, and machine hours 91,400. Compute the predetermined overhead rate for each activity base. (Round answers to 2 decimal places, e.g. 10.50% or 10.50.) Overhead rate per direct labor cost Overhead rate per direct labor hour Overhead rate per machine hour
THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. Test Company uses an activity-based cost...
THE FOLOWING INFORMATION IS USED FOR QUESTIONS 11 – 13. Test Company uses an activity-based cost system and has identified the following overhead activities, estimated costs, cost drivers, and estimated usage for the coming period. Activity Estimated Cost Cost Driver Estimated Usage Setting up $120,000 Number or setups 300 setups Ordering 90,000 Number of orders 9,000 orders Machining      210,000 Machine hours 20,000 machine hours $420,000 Test Company expects to use 10,500 direct labor hours for the period. The accounting...