Question

Flexible Budget, Multiple Regression The controller for Muir Company's Salem plant is analyzing overhead in order...

Flexible Budget, Multiple Regression

The controller for Muir Company's Salem plant is analyzing overhead in order to determine appropriate drivers for use in flexible budgeting. She decided to concentrate on the past 12 months since that time period was one in which there was little important change in technology, product lines, and so on. Data on overhead costs, number of machine hours, number of setups, and number of purchase orders are in the following table.

Month Overhead Costs Machine Hours Number of
Setups
Number of
Purchase Orders
January $ 32,296 1,000 20    216
February 31,550 930 18    250
March 36,280 1,100 21    300
April 36,867 1,050 23    270
May 36,790 1,170 22    285
June 37,800 1,200 25    240
July 40,024 1,235 27    237
August 39,256 1,190 24    303
September 33,800 1,070 20    255
October 33,779 1,210 22    195
November 37,225 1,207 23    270
December 27,500 1,084 15    150
Totals $423,167 13,446 260    2,971

Required:

1. Run a multiple regression equation using machine hours, number of setups, and number of purchase orders as independent variables. Prepare a flexible budget for overhead for the 12 months using the results of this regression equation. (Round the regression coefficients to the nearest cent and predicted overhead to the nearest dollar.)

If there is no variance, enter "0" for the amount and select "NA" in the last column. Enter all your answers as positive amounts.

Muir Company
Flexible Budget for Overhead
Month Predicted Overhead Actual Overhead Variance
January $ $ $
February
March
April
May
June
July
August
September
October
November
December
Totals $ $ $

2. Now, suppose that the controller remembers that the factory throws two big parties each year, one for the 4th of July and the other for Christmas. Rerun the multiple regression with machine hours, number of setups, and number of purchase orders, and add a dummy variable called “Party.” (This variable takes the value one for months with a factory-sponsored party, and zero otherwise.) Prepare a flexible budget for the 12 months using the results of this regression. (Round the regression coefficients to the nearest cent and each predicted overhead amount to the nearest dollar.)

If there is no variance, enter "0" for the amount and select "NA" in the last column. Enter all your answers as positive amounts.

Muir Company
Flexible Budget for Overhead
Month Predicted Overhead Actual Overhead Variance
January $ $ $
February
March
April
May
June
July
August
September
October
November
December
Total $ $ $

Homework Answers

Answer #1

Answer:1 Overhead rate=Total overhead cost/Total estimated machine hours

=$423167/13446

=$31.47 per hour

Month

Machine hours

Predicted overhead

Actual Overhead

Variance

Type F or U

Jan

1000

31470

32296

-826

U

Feb

930

29267.1

31550

-2282.9

U

Mar

1100

34617

36280

-1663

U

Apr

1050

33043.5

36867

-3823.5

U

May

1170

36819.9

36790

29.9

F

Jun

1200

37764

37800

-36

U

Jul

1235

38865.5

40024

-1158.6

U

Aug

1190

37449.3

39256

-1806.7

U

Sep

1070

33672.9

33800

-127.1

U

Oct

1210

38078.7

33779

4299.7

F

Nov

1207

37984.3

37225

759.29

F

Dec

1084

34113.5

27500

6613.48

F

Total

13446

423146

423167

-21.38

U

Answer2:

Overhead cost= $8699.64+ $23.71(machine hours)

Month

Machine hours

Predicted overhead

Actual Overhead

Variance

Type F or U

Jan

1000

32410

32296

114

F

Feb

930

30750

31550

800

U

Mar

1100

34781

36280

1499

U

Apr

1050

33595

36867

3272

U

May

1170

36440

36790

350

U

Jun

1200

37152

37800

648

U

Jul

1235

37981

40024

2043

U

Aug

1190

36915

39256

2341

U

Sep

1070

34069

33800

269

F

Oct

1210

37389

33779

3610

F

Nov

1207

37318

37225

93

F

Dec

1084

34401

27500

6901

F

Total

13446

423201

423167

34

F

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Dri
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       DriverFixed              Cost                Variable Rate Maintenance            Machine hours         $40,000         $ 2.50 Machining                 Machine hours          25,000            3.00 Setting up                  Setups                            -                  2,250 Purchasing               Purchase orders        75,000           6.00 Cohlmia has found that the following driver levels are associated with two different levels of production. Driver                                     40,000 units              60,000 units Machine hours                     60,000                       90,000 Setups                                          50                   70 Purchase orders                  10,000                       16,000 Required: Prepare an activity-based flexible budget.
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Driver F
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Driver Fixed              Cost                Variable Rate Maintenance            Machine hours         $40,000          $ 2.50 Machining                 Machine hours         25,000             3.00 Setting up                  Setups                            -                 2,250 Purchasing               Purchase orders       75,000             6.00 Cohlmia has found that the following driver levels are associated with two different levels of production. Driver                                     40,000 units              60,000 units Machine hours                     60,000                        90,000 Setups                                          50                               70 Purchase orders                   10,000                        16,000 Required: Prepare...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 8,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $70,400    Power and light 3,520    Indirect materials 17,600       Total variable overhead cost $91,520 Fixed overhead cost:    Supervisory salaries $32,030    Depreciation of plant and equipment 20,130    Insurance and property taxes 12,810       Total fixed overhead cost 64,970 Total factory...
Using Regression Results to Construct and Apply a Cost Formula Dohini Manufacturing Company had the following...
Using Regression Results to Construct and Apply a Cost Formula Dohini Manufacturing Company had the following 12 months of data on purchasing cost and number of purchase orders. Month Purchasing Cost Number of Purchase Orders January $18,860        370                  February 18,065        330                  March 19,250        370                  April 18,050        410                  May 19,345        400                  June 19,500        450                  July 19,670        460                  August 20,940        560                  September 19,430        440                  October 20,020        500                  November 18,800        470                  December 19,340        480                  The controller for Dohini Manufacturing ran regression on the...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $160,200    Power and light 5,940    Indirect materials 52,200       Total variable overhead cost $218,340 Fixed overhead cost:    Supervisory salaries $76,420    Depreciation of plant and equipment 48,030    Insurance and property taxes 30,570       Total fixed overhead cost 155,020 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 11,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $106,700    Power and light 4,400    Indirect materials 29,700       Total variable overhead cost $140,800 Fixed overhead costs:    Supervisory salaries $49,280    Depreciation of plant and equipment 30,980    Insurance and property taxes 19,710       Total fixed overhead cost 99,970 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 12,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $87,600    Power and light 5,280    Indirect materials 38,400       Total variable overhead cost $131,280 Fixed overhead cost:    Supervisory salaries $45,950    Depreciation of plant and equipment 28,880    Insurance and property taxes 18,380       Total fixed overhead cost 93,210 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $152,000    Power and light 7,200    Indirect materials 46,400       Total variable overhead cost $205,600 Fixed overhead costs:    Supervisory salaries $71,960    Depreciation of plant and equipment 45,230    Insurance and property taxes 28,780       Total fixed overhead cost 145,970 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 10,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $84,000 Power and light 3,800 Indirect materials 22,000 Total variable overhead cost $109,800 Fixed overhead cost: Supervisory salaries $38,430 Depreciation of plant and equipment 24,160 Insurance and property taxes 15,370 Total fixed overhead cost 77,960 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $64,800    Power and light 3,870    Indirect materials 20,700       Total variable overhead cost $89,370 Fixed overhead cost:    Supervisory salaries $31,280    Depreciation of plant and equipment 19,660    Insurance and property taxes 12,510       Total fixed overhead cost 63,450 Total factory...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT