Question

he following information applies to the questions displayed below.]   Cost standards for one unit of product...

he following information applies to the questions displayed below.]

  Cost standards for one unit of product no. C77:
     Direct material 3 pounds at $2.80 per pound $8.40
     Direct labor 6 hours at $7.40 per hour 44.40
  Actual results:
     Units produced 6,600 units
     Direct material purchased 26,200 pounds at $3.00 $78,600
     Direct material used 19,500 pounds at $3.00 58,500
     Direct labor 40,700 hours at $7.20 293,040

Assume that the company computes variances at the earliest point in time. The direct-labor efficiency variance is:

Assume that the company computes variances at the earliest point in time. The standard hours allowed for the work performed are:

Homework Answers

Answer #1

Direct-labor efficiency variance = SR[AH-SH]

               = 7.4 [40700 -(6600 * 6)]

                   7.4 [40700- 39600]

                     8140 U

standard hours allowed for the work performed =Actual units *Standard hours per unit

         = 6600 * 6

          = 39600 hours

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following data relate to product no. 338 of Voluntown Company: Direct labor standard: 6 hours...
The following data relate to product no. 338 of Voluntown Company: Direct labor standard: 6 hours at $15 per hour Direct labor used in production: 51,000 hours at a cost of $775,200 Manufacturing activity: 8,400 units completed The direct-labor rate variance is: Multiple Choice None of the answers is correct. $10,200U. $10,080U. $10,080F. Cost standards for one unit of product no. C1895: Direct material 3 pounds at $2.70 per pound $ 8.10 Direct labor 7 hours at $7.70 per hour...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 6 pounds at $8.00 per pound $ 48.00 Direct labor: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard variable cost per unit $ 105.00 The company also established the following cost formulas...
Required information [The following information applies to the questions displayed below.] Morganton Company makes one product...
Required information [The following information applies to the questions displayed below.] Morganton Company makes one product and it provided the following information to help prepare the master budget: The budgeted selling price per unit is $60. Budgeted unit sales for June, July, August, and September are 8,000, 11,000, 13,000, and 14,000 units, respectively. All sales are on credit. Thirty percent of credit sales are collected in the month of the sale and 70% in the following month. The ending finished...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 6 pounds at $8.00 per pound $ 48.00 Direct labor: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard variable cost per unit $ 105.00 The company also established the following cost formulas...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable...
[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $9.00 per pound $ 45.00 Direct labor: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard variable cost per unit $ 114.00 The company also established the following cost formulas...
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 62,900 lbs. @ $8.10 per lb. Direct labor 3 hrs. @ $17 per hr. 26,400 hrs. @ $17.50 per hr. Overhead 3 hrs. @ $13 per hr. $ 352,500 Units manufactured 8,900 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...
[The following information applies to the questions displayed below.] Morganton Company makes one product and it...
[The following information applies to the questions displayed below.] Morganton Company makes one product and it provided the following information to help prepare the master budget for its first four months of operations: a. The budgeted selling price per unit is $65. Budgeted unit sales for June, July, August, and September are 9,300, 24,000, 26,000, and 27,000 units, respectively. All sales are on credit. b. Forty percent of credit sales are collected in the month of the sale and 60%...
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $11.00 per kg $ 55.00   Direct labour: 3 hours at $12 per hour 36.00   Variable overhead: 3 hours at $7 per hour 21.00   Total standard cost per unit $ 112.00   The company planned to produce and sell 21,000...
Required information [The following information applies to the questions displayed below.] Morganton Company makes one product...
Required information [The following information applies to the questions displayed below.] Morganton Company makes one product and it provided the following information to help prepare the master budget: The budgeted selling price per unit is $60. Budgeted unit sales for June, July, August, and September are 8,900, 20,000, 22,000, and 23,000 units, respectively. All sales are on credit. Forty percent of credit sales are collected in the month of the sale and 60% in the following month. The ending finished...
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product....
Required information [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 3 hours at $15 per hour 45.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard variable cost per unit $ 112.00 The company also established the following...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT