10-1 What is a quality standard? What is price standard?

10-2 Why are separate price and quantity variance computed?

10-3 Who is generally responsible for the materials price variance? the materials quantity varience? the labor efficiency varience?

Homework Answers

Answer #1

10-1) A Quantity standard is the amount of materials that should be used in the production of a single unit. Price standard is the price that should be paid for materials at a given level of activity.

10-2) Price and quantity variances are seperately computed because seperating price and quantity variances gives insight into what causes variances to be favorable or unfavorable, and is a tool useful for seeing if costs were too high or if too much material was used.

10-3) The materials price variance is usually the responsibility of the purchasing manager. The materials quantity and labor efficiency variances are usually the responsibility of production managers and supervisors.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Who is generally responsible for the materials price variance? The materials quantity variance? The labor efficiency...
Who is generally responsible for the materials price variance? The materials quantity variance? The labor efficiency variance?
Which of the following statements is false? 1) A residual income of zero is acceptable. 2)...
Which of the following statements is false? 1) A residual income of zero is acceptable. 2) A positive residual income is acceptable. 3) A negative residual income is unacceptable. 4) The last budget prepared is the cash budget. 5) The first budget prepared is the sales budget. The manager of an investment center is: 1) Responsible for controlling costs only. 2) Responsible for control costs and generating revenues only. 3) Responsible for controlling costs, generating revenues and investing in operating...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 6.00 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis...
Exercise 10-6 Direct Materials and Direct Labor Variances [LO10-1, LO10-2] Huron Company produces a commercial cleaning...
Exercise 10-6 Direct Materials and Direct Labor Variances [LO10-1, LO10-2] Huron Company produces a commercial cleaning compound known as Zoom. The direct materials and direct labor standards for one unit of Zoom are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 6.80 pounds $ 2.90 per pound $ 19.72 Direct labor 0.20 hours $ 9.00 per hour $ 1.80 During the most recent month, the following activity was recorded: 15,100.00 pounds of material were...
Raw materials purchased had a lower price than the standard price. The materials were found to...
Raw materials purchased had a lower price than the standard price. The materials were found to be of inferior quality. Accordingly, each unit of product consumed more materials than the amount that should have been used. Direct labor workers ended up taking longer to complete products because the inferior materials got jammed in the machinery, and slowed down machinery. Which of the following is likely to be the result of buying these inferior materials? Group of answer choices An unfavorable...
1. The standard materials cost to produce 1 unit of Product R is 6 pounds of...
1. The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50 per pound. In manufacturing 8,000 units, 47,000 pounds of material were used at a cost of $51 per pound. What is the direct materials quantity variance? 2. The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50 per pound. In manufacturing 8,000 units, 47,000 pounds...
Bulluck Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...
Bulluck Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Direct materials 5.50 grams $ 3.00 per gram Direct labor 0.60 hours $ 31.00 per hour Variable overhead 0.60 hours $ 4.00 per hour The company reported the following results concerning this product in July. Actual output 5,000 units Raw materials used in production 13,370 grams Actual direct labor-hours 2,780 hours Purchases of raw materials 14,100 grams Actual price of raw materials...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $45,210, all of which were used in the production of 2,500 units of product. In addition, 4,100 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $42,660, all of which were used in the production of 2,250 units of product. In addition, 4,600 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $52,740, all of which were used in the production of 2,750 units of product. In addition, 4,500 direct labor-hours were worked on the product during the month. The...