Merrill Corp. has the following information available about a
potential capital investment:
Initial investment | $ | 1,500,000 | |||||
Annual net income | $ | 150,000 | |||||
Expected life | 8 | years | |||||
Salvage value | $ | 160,000 | |||||
Merrill’s cost of capital | 10 | % | |||||
Assume straight line depreciation method is
used.
Required:
1. Calculate the project’s net present value. (Future
Value of $1, Present Value of $1, Future Value Annuity of $1,
Present Value Annuity of $1.) (Use appropriate factor(s)
from the tables provided. Do not round intermediate calculations.
Round the final answer to nearest whole dollar.)
Net Present Value |
2. Without making any calculations, determine
whether the internal rate of return (IRR) is more or less than 10
percent.
Less than 10 Percent OR |
|
Greater than 10 Percent |
3. Calculate the net present value using a 13
percent discount rate. (Future Value of $1, Present Value of $1,
Future Value Annuity of $1, Present Value Annuity of $1.)
(Use appropriate factor(s) from the tables provided. Do not
round intermediate calculations. Round the final answer to nearest
whole dollar.)
Net Present Value |
4. Without making any calculations, determine
whether the internal rate of return (IRR) is more or less than 13
percent.
More than 13 percent OR |
|
Less than 13 percent OR |
|
Equal to 13 percent |
(1). Net present value pf the project = $268480
Explanation;
First of all let’s calculate annual cash flows;
Annual cash flow = Annual net income + Depreciation
Annual net income is given = $150000
Depreciation ($1500000 – $160000) / 8 = $167500
Thus annual cash flow ($150000 + $167500) = $317500
Now let’s calculate project’s net present value;
Year |
Annual cash flows |
Discounting factor @ 10% |
Present value |
0 |
($1500000) |
1 |
($1500000) |
1 |
$317500 |
(1 + 0.10)1 |
$288636.36 |
2 |
$317500 |
(1 + 0.10)2 |
$262396.69 |
3 |
$317500 |
(1 + 0.10)3 |
$238542.45 |
4 |
$317500 |
(1 + 0.10)4 |
$216856.77 |
5 |
$317500 |
(1 + 0.10)5 |
$197142.52 |
6 |
$317500 |
(1 + 0.10)6 |
$179220.47 |
7 |
$317500 |
(1 + 0.10)7 |
$162927.7 |
8 |
$477500 |
(1 + 0.10)8 |
$222757.27 |
Net present value of project |
$268480.23 |
(2). IRR is greater than 10%
Explanation;
As we have seen that at 10% net present is more than $0 hence IRR must be greater than 10% because as per rule of IRR NPV should be zero but at 10% NPV is more than zero hence IRR will be greater than 10%.
(3). Net present value pf the project = $83795
Explanation;
First of all let’s calculate annual cash flows;
Annual cash flow = Annual net income + Depreciation
Annual net income is given = $150000
Depreciation ($1500000 – $160000) / 8 = $167500
Thus annual cash flow ($150000 + $167500) = $317500
Now let’s calculate project’s net present value;
Year |
Annual cash flows |
Discounting factor @ 13% |
Present value |
0 |
($1500000) |
1 |
($1500000) |
1 |
$317500 |
(1 + 0.13)1 |
$280973.45 |
2 |
$317500 |
(1 + 0.13)2 |
$248649.07 |
3 |
$317500 |
(1 + 0.13)3 |
$220043.43 |
4 |
$317500 |
(1 + 0.13)4 |
$194728.7 |
5 |
$317500 |
(1 + 0.13)5 |
$172326.28 |
6 |
$317500 |
(1 + 0.13)6 |
$152501.13 |
7 |
$317500 |
(1 + 0.13)7 |
$134956.75 |
8 |
$477500 |
(1 + 0.13)8 |
$179616.33 |
Net present value of project |
$83795.14 |
(4). IRR is more than 13%
Explanation;
As we have seen that at 13% net present is more than $0 hence IRR must be greater than 13% because as per rule of IRR NPV should be zero but at 13% NPV is more than zero hence IRR will be greater than 13%.
Get Answers For Free
Most questions answered within 1 hours.