Q.1 For Divaxo Company, labor-hours are 28,000 and wages $126,000 at the high point of the relevant range, and labor-hours are 20,000 and wages $102,000 at the low point of the relevant range.
What is the estimated total labor costs at Divaxo Company when 11,100 labor-hours are used?
$52,725 |
||
$75,300 |
||
$49,950 |
||
$56,610 |
Using the high low method we will first compute the variable cost per labor hour
y2 = $126,000 and y1 = $102,000
x2 = 28,000 hours and x1 = 20,000 hours
Thus variable cost per labor hour = (126,000-102,000)/(28,000-20,000)
= 24,000/8,000
$3 per labor hour
Thus the cost equation is y = a+3x.
So a = y2-bx2 = 126,000 - (3*28,000)
= 126,000 - 84,000
= 42,000
When 11,100 labo hours is used then cost will be:
42,000+(11,100*3)
= 42000+33300
= $75,300 (i.e. the 2nd option)