Question

There are 3 parts to this 1 question. Here is the information: Last year your construction...

There are 3 parts to this 1 question.

Here is the information:

Last year your construction company built a 100,000 SF, five-story parking garage for $5,395,621. The parking garage included one elevator, which cost $126,345, and its costs are included in the $5,395,621 cost. It is estimated that all costs have been risen three percent during the last year. Using this information prepare a preliminary cost estimate for the each two part for a 95,000 SF, five-story garage with two elevators.

Part 1-

What is the cost of the new parking garage without elevators? Answer should be $5,156,000 please explain how you get this part.

Part 2-

What is the total cost of the new parking garage? Answer should be $5,258,000 please explain how you get this part.

Homework Answers

Answer #1
ans 1
Cost per sqaure feet excluding elevator
(5395621-126345)/100000 52.69 per sq ft
not rounded off rounded off
Cost without elevator 5005812 5005550
$52.69*95000
Add: Elevators (2*126345) 252690 252690
Total A 5258502 5258240
Add: Adjustment for infation 3% 3%
Amt of inflation B 157755 157747
Prelimainary cost estimate (after inflation )A+B 5416257 5415987
If we round off for proper calculation than take it as 5420000 5420000
ans 2
cost of the new parking garage without elevators
Cost without elevator 5005812
Add: Inflation 150174
cost of the new parking garage without elevators 5155987
If rounded off to nearest hundred $5156000
ans 3
total cost of the new parking garage without inflation 5258240
(from working in ans 1)
So rounded off too 000 5258000
If any doubt please comment
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Information for Garland Construction for last year:   Sales $2,000,000 Variable costs $1,200,000 Traceable fixed costs $200,000...
Information for Garland Construction for last year:   Sales $2,000,000 Variable costs $1,200,000 Traceable fixed costs $200,000 Average invested capital (assets) $3,000,000 Current liabilities $200,000 Required rate of return 15% Marginal tax rate 36% Weighted average cost of capital 12% Solve 1. residual income. 2. return on investment. 3. Calculate the economic value added
Last year (2017), Maginnis Condos installed a mechanized elevator for its tenants. The owner of the...
Last year (2017), Maginnis Condos installed a mechanized elevator for its tenants. The owner of the company, Mitch Maginnis, recently returned from an industry equipment exhibition where he watched a computerized elevator demonstrated. He was impressed with the elevator’s speed, comfort of ride, and cost efficiency. Upon returning from the exhibition, he asked his purchasing agent to collect price and operating cost data on the new elevator. In addition, he asked the company’s accountant to provide him with cost data...
Last year (2016), Richter Condos installed a mechanized elevator for its tenants. The owner of the...
Last year (2016), Richter Condos installed a mechanized elevator for its tenants. The owner of the company, Ron Richter, recently returned from an industry equipment exhibition where he watched a computerized elevator demonstrated. He was impressed with the elevator's speed, comfort of ride, and cost efficiency. Upon returning from the exhibition, he asked his purchasing agent to collect price and operating cost data on the new elevator. In addition, he asked the company’s accountant to provide him with cost data...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
1. A city with 4% unemployment and no inflation is considering building a new stadium for...
1. A city with 4% unemployment and no inflation is considering building a new stadium for its professional football team. The team currently plays in an old stadium owned by the city. If a new stadium were to be built, it would cost city $400M (M for million) to demolish the old one and build the new one. The new stadium would be expected to last for 40 years and the city would finance the costs of the project by...
1. A city with 4% unemployment and no inflation is considering building a new stadium for...
1. A city with 4% unemployment and no inflation is considering building a new stadium for its professional football team. The team currently plays in an old stadium owned by the city. If a new stadium were to be built, it would cost city $400M (M for million) to demolish the old one and build the new one. The new stadium would be expected to last for 40 years and the city would finance the costs of the project by...
Problem 20-4A (Part Level Submission) Last year (2016), Richter Condos installed a mechanized elevator for its...
Problem 20-4A (Part Level Submission) Last year (2016), Richter Condos installed a mechanized elevator for its tenants. The owner of the company, Ron Richter, recently returned from an industry equipment exhibition where he watched a computerized elevator demonstrated. He was impressed with the elevator's speed, comfort of ride, and cost efficiency. Upon returning from the exhibition, he asked his purchasing agent to collect price and operating cost data on the new elevator. In addition, he asked the company’s accountant to...
    Use the following information for this question:                    June 1          &
    Use the following information for this question:                    June 1                 Inventory 100 @ $1.00                             6                 Purchased 150 @ $1.10                           13                 Purchased   50 @ $1.20                           20                 Purchased 100 @ $1.30                           25                 Purchased   25 @ $1.40                                                                                          Total Units Sold in June: 300 units Using the first-in, first-out (FIFO) method, the cost assigned to the ENDING INVENTORY (not Cost of Goods Sold) would be a. $325 b. $362.50 c. $227.50 d. $165 19. King Co. received a $3,000 advance payment for legal services to be performed in the future....
Kristen Lu purchased a used automobile for $16,750 at the beginning of last year and incurred...
Kristen Lu purchased a used automobile for $16,750 at the beginning of last year and incurred the following operating costs:      Depreciation ($16,750 ÷ 5 years) $3,350   Insurance $1,700   Garage rent $900   Automobile tax and license $450   Variable operating cost $0.13 per mile    The variable operating cost consists of gasoline, oil, tires, maintenance, and repairs. Kristen estimates that, at her current rate of usage, the car will have zero resale value in five years, so the annual straight-line depreciation...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT