Job 652 was recently completed. The following data have been recorded on its job cost sheet.
Direct materials=$59,900
Direct labor-hours=1,225 DLHs
Direct labor wage rate= $14 per DLH
Number of units completed=3,700
The company applies manufacturing overhead on the basis of direct labor hours. The predetermined overhead rate is $32 per direct labor hour.
Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round answer to 2 decimal places.)
Unit product cost=????
Ans. | Unit product cost = Total product cost / No. of units completed | ||
116250 / 3700 | |||
31.42 per unit | |||
Calculation of Total product cost: | |||
Direct materials | 59900 | ||
Direct labor (1225*14) | 17150 | ||
Manufacturing overhead (1225*32) | 39200 | ||
Total product cost | 116250 | ||
*Cost of direct labor = Direct labor hours * direct labor wage rate | |||
*Cost of manufacturing overhead = Direct labor hours * predetermined ovehread rate | |||