1.)
The following company information is available for March. The direct materials price variance is: |
Direct materials purchased and used | 3,400 feet @ $75 per foot |
Standard costs for direct materials for March production | 3,500 feet @ $73 per foot |
$500 favorable.
$6,800 unfavorable.
$7,000 unfavorable.
$6,800 favorable.
$7,000 favorable.
2.)
Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: |
Direct materials standard (3 lbs @ $1/lb) | $ 3 per finished unit |
Total direct materials cost variance—unfavorable | $ 25,750 |
Actual direct materials used | 120,000 lbs |
Actual finished units produced | 30,000 units |
$25,750 unfavorable.
$4,250 favorable.
$30,000 unfavorable.
$30,000 favorable.
$25,750 favorable
3.) Levelor Company's flexible budget shows $10,740 of overhead at 75% of capacity, which was the operating level achieved during May. However, the company applied overhead to production during May at a rate of $2.00 per direct labor hour based on a budgeted operating level of 6,150 direct labor hours (90% of capacity). If overhead actually incurred was $11,216 during May, the controllable variance for the month was:
$476 unfavorable.
$476 favorable.
$1,560 favorable.
$1,560 unfavorable.
$1,084 favorable.
4.)
The standard materials cost to produce 1 unit of Product R is 9 pounds of material at a standard price of $53 per pound. In manufacturing 5,000 units, 44,000 pounds of material were used at a cost of $54 per pound. What is the total direct materials cost variance? |
$9,000 unfavorable.
$54,000 unfavorable.
$54,000 favorable.
$9,000 favorable.
$45,000 unfavorable.
Get Answers For Free
Most questions answered within 1 hours.