Question

Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....

Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which took 44,500 machine hours. Actual fixed overhead costs for the year amounted to $270,600 while the actual variable overhead cost per unit was $3.70.

Required: (Do not round intermediate calculations. Round your final answer to the nearest whole dollar amount.)

A. Based on the information provided above, what was the fixed overhead spending (budget) variance for the year?

B. What was the fixed overhead production volume variance for the year?

C. Based on the information provided above, what was the variable overhead spending variance for the year?

D. What was the variable overhead efficiency variance for the year?

Homework Answers

Answer #1

Answer

A.The fixed overhead spending (budget) variance for the year:

= Actual fixed overhead costs ? Budgeted fixed overhead

= $270,600 ? $277,500

= $6,900 F

B.The fixed overhead production volume variance for the year:

Budgeted fixed overhead ? Applied fixed overhead

= $277,500 ? (21,600 units × 2 hrs./unit(55500/27750) × $5/hr.(277500/55500))

= $277,500 ? $216,000

= $61,500 U

C.The variable overhead spending variance for the year:

Actual variable overhead costs ? Flexible budget based on inputs

= ($3.70/unit × 21,600 units) ? (44,500 hours × $1.90/hr.[27750*3.80/55500])

= $79,920 ? $84,550

=$4,630 F

D.

The variable overhead efficiency variance for the year:

Flexible budget based on Inputs ? Flexible budget based on Output

= $84,550 ? (21,600 units × 2 hrs./unit × $1.90/hr.)

= $84,550 ? $82,080

=$2,470 U

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,700 units, which...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.40 Planned activity during the period: 19,000 machine hours Actual production: 12,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $153,180 Actual total overhead: $432,900 Actual machine hours worked: 22,200 Required: 1. Calculate the...
Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual...
Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours. (Practical capacity is 500,000 hours.) Annual budgeted overhead costs total $739,200, of which $532,800 is fixed overhead. A total of 119,400 units using 478,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $241,900, and actual fixed overhead costs...
Chocolate, Inc., uses a standard costing system and develops its overhead rates from the current annual...
Chocolate, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 145,000 units requiring 620,000 direct labor hours. (Practical capacity is 630,000 hours.) Annual budgeted overhead costs total $802,600, of which $585,800 is fixed overhead. A total of 143,400 units using 619,200 direct labor hours were produced during the year. Actual variable overhead costs for the year were $275,800, and actual fixed overhead costs...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October: Master budget data: Units 2,500 Total machine hours (denominator volume) 100,000 Total variable overhead cost $ 250,000 Total fixed overhead cost $ 50,000 Actual operating results: Variable overhead cost incurred $ 265,000 Fixed overhead cost incurred $ 54,000 Units manufactured 2,250 Total machine hours 96,000 Required: Compute the following variances using machine hours as the activity variable used to assign...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $772,440, of which $551,040 is fixed overhead. A total of 119,300 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT