Question

A company has two products: A and B. It uses activity-based costing and has prepared the...

A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:

Budgeted Activity
Activity Cost Pool Budgeted Cost Product A Product B
Activity 1 $ 102,000 4,500 4,300
Activity 2 $ 77,000 6,000 7,000
Activity 3 $ 123,000 4,000 6,750


Annual production and sales level of Product A is 35,800 units, and the annual production and sales level of Product B is 71,050 units. What is the approximate overhead cost per unit of Product A under activity-based costing?

Multiple Choice

  • $3.73

  • $1.56

  • $2.37

  • $10.27

  • $11.59

Homework Answers

Answer #1
(iv) (i) (ii) (iii) = (i) + (ii) (v) = (iv)/(iii) (i) x (v)
Activity Cost Pool Budgeted Cost Product A Product B Total Budgeted Activity Activity Rate Overhead allocated to Product A
Activity 1 102,000 4,500 4,300 8,800 11.59090909 52,159
Activity 2 77,000 6,000 7,000 13,000 5.923076923 35,538
Activity 3 123,000 4,000 6,750 10,750 11.44186047 45,767
Total 133,465

Units produce of Product A = 35,800

Total cost allocated to Product A = $133,465

Overhead cost per unit of Product A = Total cost allocated to Product A/ Units produce of Product A

= 133,465/35,800

= $3.73

The approximate overhead cost per unit of Product A under activity-based costing is $3.73

First option is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Activity 1 $ 87,000 3,000 2,800 Activity 2 $ 62,000 4,500 5,500 Activity 3 $ 93,000 2,500 5,250 Annual production and sales level of Product A is 34,300 units, and the annual production and sales level of Product...
1.A company has two products: A and B. It uses activity-based costing and has prepared the...
1.A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Activity Cost Pool Budgeted Cost Product A Product B Activity 1 $ 87,000 3,000 2,800 Activity 2 $ 62,000 4,500 5,500 Activity 3 $ 93,000 2,500 5,250 Annual production and sales level of Product A is 34,300 units, and the annual production and sales level of Product B is...
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Activity 1 $ 89,000 3,200 3,000 Activity 2 $ 64,000 4,700 5,700 Activity 3 $ 97,000 2,700 5,450 Annual production and sales level of Product A is 34,500 units, and the annual production and sales level of Product...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A1 Product B2 Activity 1 $ 59,000 2,300 5,900 Activity 2 $ 74,000 3,340 5,860 Activity 3 $ 102,000 8,300 1,900 Annual production and sales level of Product A1 is 9,580 units, and the annual production and sales level of Product...
Bridget Company uses activity-based costing. The company has two products: A and B. The annual production...
Bridget Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 2,000 units and of Product B is 3,000 units. There are three activity cost pools, with estimated total cost and expected activity as follows: Expected Activity Activity Cost Pool Estimated Cost Product A Product B Total Activity 1 $9,000 400 350 750 Activity 2 12,000 100 400 500 Activity 3 48,000 400 1,200 1,600 The cost per unit...
Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production...
Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 11,000 units and of Product B is 8,500 units. There are three activity cost pools, with total cost and total activity as follows: Total Activity Activity Cost Pool Total Cost Product A Product B Total Activity 1 $29,200 150 580 730 Activity 2 $40,150 850 250 1,100 Activity 3 $105,570 830 3,310 4,140 The activity-based costing cost per...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
1. A company uses activity-based costing to determine the costs of its three products: A, B,...
1. A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 89,000 7,900 10,900 21,900 Activity 2 $ 64,000 8,900 16,900 9,900 Activity 3 $ 120,000 4,400 2,900 3,525 How much overhead will be assigned to Product...
3. Borleau Corporation has an activity-based costing system with three activity cost pools-- Supporting direct labor,...
3. Borleau Corporation has an activity-based costing system with three activity cost pools-- Supporting direct labor, Setting up machines, and General factory. The company makes two products: Basic Product and Deluxe Product. Annual production and sales are 1,700 units of Basic Product and 1,100 units of Deluxe Product. The estimated overhead costs and expected activity for next period are as follows: Activity Cost Pools and Activity measures Estimated Overhead Costs Expected Activity Basic Product Deluxe Product Supporting direct labor (DLHs)...
Murphy Company produces two products: Standard and Deluxe. The company uses an activity-based costing system. Murphy...
Murphy Company produces two products: Standard and Deluxe. The company uses an activity-based costing system. Murphy produces 8,000 units of Standard and 2,000 units of Deluxe. The company uses two activity cost pools, with estimated total cost and activity as follows: Expected Activity Activity Cost Pool Estimated Cost Standard Deluxe #1 $12,000 500 250 #2 $24,000 400 1,200 What is the cost per unit of Deluxe under activity-based costing? $1.75 $11.00 $15.00 $16.00
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT