Question

XYZ Company uses the formula y = a + bX to predict and analyze overhead costs....

XYZ Company uses the formula y = a + bX to predict and analyze overhead costs. In the previous year, XYZ used $1,750 per month for the a factor and $0.35 for the b factor in applying overhead. XYZ has used direct labour hours in the past, but is wondering whether overhead behaviour is more closely associated with machine hours. The following data have been generated for consideration: Month Machine Hours Overhead Costs 1 466 $2,785 2 479 $3,069 3 405 $2,456 4 484 $2,888 5 508 $2,804 6 418 $2,515 Determine the fixed and variable values, using machine hours. (Round variable cost to 2 decimal places, e.g. 15.25 and fixed cost to 0 decimal places, e.g. 525). Fixed Cost $ Variable Cost $ per machine hour

Homework Answers

Answer #1

Calculation of Variable cost:

High level activity cost = cost at 508 machine hours =$2804

Low level activity cost = cost at 405 machine hours = $2456

Variable cost =(Cost at high activity level – Cost at low activity level) / (High activity level – low activity level) = ($2804-$2456) / (508 hour – 405 hour) = $348/103 =$ 3.38 per machine hour

Calculation of Fixed cost:

We can find fixed cost using the variable cost per machine hour at the high level of activity

Variable cost at high activity level = Variable cost per machine hour x Machine hours = $3.38 x 508 =$1717.04

Fixed cost = Total cost at high activity level – variable cost at high activity level =$2804 - $1717.04 =$1086.96 rounded to $1087

Conclusion

Variable cost per machine hour = $3.38

Fixed cost -$1087

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours Total Overhead Cost   September 112,800 $ 781,512   October 89,200 $ 662,568   November 157,200 $ 1,005,288   December 165,000 $ 1,044,600 Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:   Utilities (variable) $ 233,704   Supervisory salaries       and depreciation (fixed) 172,000   Maintenance (mixed)      256,864   Total overhead...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
1. X Company uses account analysis to estimate total overhead costs for each month, with units...
1. X Company uses account analysis to estimate total overhead costs for each month, with units produced as the activity measure. In May, when production was 1,000 units, the plant manager classified each overhead cost item as fixed and variable as follows: Cost Item Total Cost Cost Behavior Utilities    $21,200   100% variable Supplies     23,100 60% variable Maintenance     20,000 100% fixed If September production is expected to be 1,180 units, what are estimated total overhead costs in September (round unit costs...
XYZ Company has two production departments, Machining and Customizing. The company uses a job-order costing system...
XYZ Company has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate (POHR) in each department. The Machining Department's POHR is based on machine-hours (Mhrs) and the Customizing Department's POHR is based on direct labor-hours (DLH). At the beginning of the current year, the company estimated the following yearly Mhrs and DLH to be used in each department: 20,000 Mhrs and 15,000 DLH in the Marching Department; 10,000 Mhrs and...