Question

Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per...

Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per hour. Juliet Pants actually used 10,350 direct labour hours at a cost of $15.80 per hour to produce 50,000 pants.

a) Calculate the direct labour rate variance: $

b) Is the direct labour rate variance favourable or unfavourable?

c) Calculate the direct labour efficiency variance: $

d) Is the direct labour efficiency variance favourable or unfavourable?

e) Calculate the total direct labour variance: $

f) Is the total direct labour variance favourable or unfavourable?

Homework Answers

Answer #1
A) Direct labor rate variance
(Actual Rate - standard rate)*actual direct labor hrs
(15.80 - 16)*10,350
2070 F
b) Favourable
c) Direct labor Efficiency Variance
(Actual hours - standard hours)*Standard rate
(10,350   - 50,000*.20)*16
5600 U
d) unfavourable
e) Total direct labor variance
(actual cost - standard cost)
15.8*10350   - 50,000*.2*16
3530 U
f) unfavourable
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one car cover are as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 9.0 metres of cloth $ 10 per metre $ 90.00   Direct labour 0 hours $ 20 per hour $ 7   Variable overhead 0 hours $ 8 per hour $ 3 Budgeted fixed overhead cost is $17,400, and the normal production volume is 2,885 car covers. Overhead is...
The Clark Company makes a single product and uses standard costing. Some data concerning this product...
The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow: Labour rate variance $7,000 favourable Labour efficiency variance $12,000 favourable Variable overhead efficiency variance $4,000 favourable Number of units produced 10,000 Standard labour rate per direct labour hour $12 Standard variable overhead rate per direct labour hour $4 Actual labour hours used 14,000 Actual variable manufacturing overhead costs $58,290 1) What was the variable overhead spending variance for...
Lulu Lemon Pants is planning on producing 40,000 pants in the year. Each pant requires 0.60...
Lulu Lemon Pants is planning on producing 40,000 pants in the year. Each pant requires 0.60 metres of material at $4 per metre and 0.15 hour of direct labour at $18 per hour. Overhead is applied at the rate of $8 per direct labour hour. Calculate the following budgeted costs: a) Total metres of direct materials required to produce 40,000 pants: Answer metres b) Total direct material cost to produce 40,000 pants: $ Answer c) Total direct labour hours required...
The actual cost of direct labor per hour is​ $16.00 and the standard cost of direct...
The actual cost of direct labor per hour is​ $16.00 and the standard cost of direct labor per hour is​ $9.50. The direct labor hours allowed per finished unit is 0.25 hour. During the current​ period, 5,700 units of finished goods were produced using​ 3,500 direct labor hours. How much is the direct labor efficiency​ variance?
Tractor Corporation produces toy tractors. The company uses the following direct cost categories: Category Standard Inputs...
Tractor Corporation produces toy tractors. The company uses the following direct cost categories: Category Standard Inputs for 1 output Std. Cost per input Direct Materials 4.00 $12.50 Direct Labour 1.40 9.50 Direct Marketing 0.54 5.50 Actual performance and budgeted performance for the company is shown below: Actual output: (in units) 5,000 Direct Materials: Materials costs $299,000 Input purchased and used 23,000 Actual price per input $13.00 Direct Manufacturing Labour: Labour costs $ 95,000 Labour-hours of input 9,500 Actual price per...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.85 Fixed manufacturing overhead 6.15 Total standard cost per unit $52.00 Actual costs for producing 2,690 units were as follows: Direct materials used 5,920 kg Direct materials purchased (6,730 kg) $32,304 Direct labour (6,950 hours) $67,415 Variable manufacturing costs $32,200 Fixed manufacturing costs $17,700 1....
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
The calculation of direct labour variances shows a favourable labour rate variance of​ £5,000 and an...
The calculation of direct labour variances shows a favourable labour rate variance of​ £5,000 and an unfavourable labour efficiency variance of​ £5,000. Which of the following is the best interpretation of this​ result?     A.   The departmental manager was pleased with the efficiency of working and favoured all employees with a rise in wage rates.     B.   The employees worked inefficiently and so their wages were reduced to match the cost of the lost efficiency.     C.   The employees were...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT