[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,542,000 | $ | 3,772,000 | $ | 2,074,600 | |||
Estimated costs to complete as of year-end | 5,658,000 | 1,886,000 | 0 | ||||||
Billings during the year | 2,020,000 | 4,294,000 | 3,686,000 | ||||||
Cash collections during the year | 1,810,000 | 3,800,000 | 4,390,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
Soluton 1:
Computation of % of completion, revenue recognition and Gross Profit - Westgate Construction Company | ||||||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | % of completion (D) (B/C) | Contract Price (E) |
Total Revenue to be recoganized (F) (E * D) | Revenue for current period (G) | Gross Profit (H) (G - A) |
2018 | $2,542,000.00 | $2,542,000.00 | $8,200,000.00 | 31% | $10,000,000.00 | $3,100,000.00 | $3,100,000.00 | $558,000.00 |
2019 | $3,772,000.00 | $6,314,000.00 | $8,200,000.00 | 77% | $10,000,000.00 | $7,700,000.00 | $4,600,000.00 | $828,000.00 |
2020 | $2,074,600.00 | $8,388,600.00 | $8,388,600.00 | 100% | $10,000,000.00 | $10,000,000.00 | $2,300,000.00 | $225,400.00 |