Question

Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost   March 4,214 $...

Electricity costs at Halladay Corporation’s manufacturing plant are listed below.
Machine-Hours Utility Cost
  March 4,214 $ 39,258
  April 4,278 $ 39,613
  May 4,319 $ 39,891
  June 4,242 $ 39,414
  July 4,298 $ 39,747
  August 4,310 $ 39,808
  September 4,235 $ 39,482
  October 4,311 $ 39,821
  November 4,233 $ 39,405
Halladay's Management has determined that the plant's electricity cost is a mixed cost that depends on machine-hours used at the plant.
Required:

Estimate the variable cost per machine-hour and the fixed cost per month using the high-low method. (Round your variable cost to 2 decimal places and fixed cost to the nearest dollar amount. Be sure to round variable cost to 2 decimal places in all intermediate calculations. Omit the "$" sign in your response.)

  Variable cost $   
  Fixed cost $   

Homework Answers

Answer #1
Machine Hours Utility Cost
High Activity Level                        4,319                            39,891
Low Activity Level                        4,214                            39,258
Change                            105                                  633
Variable Cost per Unit                          6.03 per Machine Hour
Fixed Cost                      13,847

Calculation:

Variable Cost per Unit 633/105                                 6.03
Fixed Cost 39891-(6.03*4319)                            13,847


Dear Student,

Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.

Also please give your positive rating.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost March 4,214 $...
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost March 4,214 $ 39,258 April 4,278 $ 39,613 May 4,319 $ 39,891 June 4,242 $ 39,414 July 4,298 $ 39,747 August 4,310 $ 39,808 September 4,235 $ 39,482 October 4,311 $ 39,821 November 4,233 $ 39,405 Halladay's Management has determined that the plant's electricity cost is a mixed cost that depends on machine-hours used at the plant. Required: Estimate the variable cost per machine-hour and the fixed...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799           $30,379           May 5,782           $30,289           June 5,764           $30,237           July 5,761           $30,233           August 5,717           $30,078           September 5,795           $30,360           October 5,809           $30,388           November 5,801           $30,378           December 5,785           $30,318         Management believes that maintenance cost is a mixed cost that depends on machine-hours. Required: Estimate the variable cost per machine-hour and...
Oriole, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity...
Oriole, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity Costs January 500 $240 February 540 $300 March 370 $210 April 440 $220 May 680 $290 June 730 $330 July 330 $180 August 530 $260 September 230 $118 October 740 $340 November 860 $370 December 600 $340 Using the high-low method, compute the variable cost of electricity per machine hour. (Round unit cost to 2 decimal places, e.g. 52.75.) Variable cost $   per machine hour...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March 4,440 $50,950 April 4,431 $50,877 May 4,412 $50,696 June 4,460 $51,113 July 4,414 $50,711 August 4,433 $50,900 September 4,443 $50,976 October 4,415 $50,730 November 4,391 $50,530 Management believes that maintenance cost is a mixed cost that depends on machine-hours. Using the high-low method, calculate a. Variable cost per machine-hour b.  Fixed cost per month c. What would total costs be for a month with 4,000...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows:...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows: Month Electricity Costs Machine Hours January $12,600 8000 February 14,333 9600 March 9,333 5600 April 15,667 10200 May 19,167 9200 June 15,134 13200 July 16,834 14400 August 15,500 12000 September 10,667 6000 October 17,667 13200 November 21,000 16800 Required: a. Using the high-low method, develop an estimate of variable electricity costs per machine hour. b. Using the high-low method, develop an estimate of fixed...
Total costs at a restaurant are listed below: Customers Served Total Cost March 11,649 $ 26,575...
Total costs at a restaurant are listed below: Customers Served Total Cost March 11,649 $ 26,575 April 11,445 $ 26,438 May 11,977 $ 26,795 June 12,200 $ 26,944 July 11,709 $ 26,615 August 11,195 $ 26,271 September 11,989 $ 26,803 October 11,680 $ 26,596 November 11,828 $ 26,695 The restaurant's total cost is a mixed cost that depends on customers served. The restaurant's management uses the high-low method to estimate the variable and fixed components of this cost. If the...
Total costs at a restaurant are listed below: Customers Served Total Cost March 11,662 $ 28,371...
Total costs at a restaurant are listed below: Customers Served Total Cost March 11,662 $ 28,371 April 11,458 $ 28,309 May 11,990 $ 28,469 June 13,500 $ 28,922 July 11,722 $ 28,389 August 11,208 $ 28,234 September 12,002 $ 28,473 October 11,693 $ 28,380 November 11,841 $ 28,424 The restaurant's total cost is a mixed cost that depends on customers served. The restaurant's management uses the high-low method to estimate the variable and fixed components of this cost. If the...
Supply costs at Coulthard Corporation's chain of gyms are listed below: Client-Visits Supply Cost March 11,661...
Supply costs at Coulthard Corporation's chain of gyms are listed below: Client-Visits Supply Cost March 11,661 $ 28,381 April 11,457 $ 28,318 May 11,989 $ 28,483 June 13,400 $ 28,920 July 11,721 $ 28,400 August 11,207 $ 28,240 September 12,001 $ 28,486 October 11,692 $ 28,391 November 11,840 $ 28,436 Management believes that supply cost is a mixed cost that depends on client-visits. Use the high-low method to estimate the variable and fixed components of this cost. Compute the variable...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours Total Overhead Cost   September 112,800 $ 781,512   October 89,200 $ 662,568   November 157,200 $ 1,005,288   December 165,000 $ 1,044,600 Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:   Utilities (variable) $ 233,704   Supervisory salaries       and depreciation (fixed) 172,000   Maintenance (mixed)      256,864   Total overhead...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT