Question

PRACTICAL QUESTION                                       &nb

PRACTICAL QUESTION                                                                                         

Tiger Construction Ltd signs a contract on 1 May 2018 to build a theme park. The construction is scheduled to commence on 1 July 2018 and the estimated date of completion is 30 June 2021. The total contract price is $5m and the cost of the park is initially estimated at $4.5m. The following data relates to the construction period:

For the year ended 30 June

2019

2020

2021

$

$

$

Costs to date

1,700,000

3,000,000

4,800,000

Estimated costs to complete

2,800,000

1,700,000

-

Progress billings to date

1,400,000

2,600,000

5,000,000

Cash received to date

1,200,000

2,200,000

5,000,000

Assume that cost (an input measure) is used as the basis for assessing progress on the construction contract.

Required

Determine the percentage of completion for 2019, 2020 and 2021.               

2019

2020

2021

$

$

$

Costs to date (A)

Estimated costs to complete (B)

Estimated total cost (A+B=C)

Percent of completion (POC=A/C)

Calculate revenue and gross profit for 2019, 2020 and 2021.                           

2019

2020

2021

$

$

$

Contract Price

Contact Price x POC

LessRevenue recognised in previous years

= Revenue recognised for the year

Less Costs for the year

= Gross profit for the year

Using the percentage of completion method, provide the journal entries for 2019, 2020 and 2021.                                                                                                              

2019

$m

2020

$m

2021

$m

(i)

To record costs incurred:

(ii)

To record billings to customers:

(iii)

To record cash collections:

(iv)

To record periodic income recognised:

Homework Answers

Answer #1

2019

2020

2021

Cost to date (A)

1700000

3000000

4800000

Estimate cost to complete (B)

2800000

1700000

Estimated total cost (A+B=C)

4500000

4700000

4800000

POC (A/C)

37.777777777%

63.829787%

100%

2019

2020

2021

Contract Price

5000000

5000000

5000000

Contract price * poc

1888889

3191489

5000000

Less:- Revenue recognised in previous years

0

1888889

3191489

Revenue recognised for the year

1888889

1302600

1808511

Less cost of the year

1700000

1300000

1800000

Gross profit of the year

188889

2600

8511

2019

2020

2021

Debit

Credit

Debit

Credit

Debit

Credit

(i)

To record cost incurred:-

Construction in Process

1700000

1300000

1800000

Account Payable

1700000

1300000

1800000

(ii)

To record billings to customer:-

Account Receivable

1400000

1200000

2400000

Billings

1400000

1200000

2400000

(iii)

To record cash collection:-

Cash

1200000

1000000

2800000

Account Receivable

1200000

1000000

2800000

(iv)

To record periodic income recognized:-

Construction in Process

188889

2600

8511

Construction Exp

1700000

1300000

1800000

Construction Revenue

1888889

1302600

1808511

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work on a two-year contract with a total price of $15,000,000. Data for 2018 and 2019 are presented below: (Follow GAAP)                                                                  2018                            2019                       Costs incurred to date             $7,200,000                  $12,050,000             Estimated costs to complete   4,800,000                         - 0 -             Billings during the year          6,000,000                      9,000,000             Collections during the year     4,200,000                      8,900,000 (a)       How much...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
SBB Construction built a building for BBB during 2019 and 2020. Relevant data are summarized below:...
SBB Construction built a building for BBB during 2019 and 2020. Relevant data are summarized below: Contract amount $ 2,550,000 Cost: 2019 1,100,000 2020 500,000 Gross profit: 2019 650,000 2020 300,000 Contract billings: 2019 1,275,000 2020 1,275,000 SBB recognizes revenue upon completion of the contract. Assume that the company bills in the exact amount of the contract (i.e. the sum of contract billings = the total contract price). What is the journal entry in 2020 to record revenue? Accounts receivable...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected to date...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT