Question

Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....

Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,700 units, which took 44,800 machine hours. Actual fixed overhead costs for the year amounted to $272,000 while the actual variable overhead cost per unit was $3.80.

3)

Based on the information provided above, what was the fixed overhead spending (budget) variance for the year?

Spending (budget) variance

Favorable

What was the fixed overhead production volume variance for the year? (Do not round intermediate calculations. Round final answer to the nearest whole dollar amount.)

Production volume variance

Unfavorable

4)

Based on the information provided above, what was the variable overhead spending variance for the year? (Do not round intermediate calculations. Round your final answer to nearest whole dollar amount.)

Spending Variance

Favorable

What was the variable overhead efficiency variance for the year? (Do not round intermediate calculations. Round your final answer to nearest whole dollar amount.)

Efficiency Variance

Unfavorable

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October: Master budget data: Units 2,500 Total machine hours (denominator volume) 100,000 Total variable overhead cost $ 250,000 Total fixed overhead cost $ 50,000 Actual operating results: Variable overhead cost incurred $ 265,000 Fixed overhead cost incurred $ 54,000 Units manufactured 2,250 Total machine hours 96,000 Required: Compute the following variances using machine hours as the activity variable used to assign...
Overhead Variances, Four-Variance Analysis, Journal Entries Laughlin, Inc., uses a standard costing system. The predetermined overhead...
Overhead Variances, Four-Variance Analysis, Journal Entries Laughlin, Inc., uses a standard costing system. The predetermined overhead rates are calculated using practical capacity. Practical capacity for a year is defined as 1,000,000 units requiring 200,000 standard direct labor hours. Budgeted overhead for the year is $750,000, of which $300,000 is fixed overhead. During the year, 900,000 units were produced using 190,000 direct labor hours. Actual annual overhead costs totaled $800,000, of which $294,700 is fixed overhead. Required: 1. Calculate the fixed...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $772,440, of which $551,040 is fixed overhead. A total of 119,300 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were...
Bluecap Co. uses a standard cost system and flexible budgets for control purposes. The following budgeted...
Bluecap Co. uses a standard cost system and flexible budgets for control purposes. The following budgeted information pertains to 2019: Denominator volume—number of units 7,000 Denominator volume—percent of capacity 70 % Denominator volume—standard direct labor hours (DLHs) 35,000 Budgeted variable factory overhead cost at denominator volume $ 102,700 Total standard factory overhead rate per DLH $ 15.10 During 2019, Bluecap worked 44,000 DLHs and manufactured 9,000 units. The actual factory overhead cost for the year was $15,000 greater than the...
The following information for the past year is available from Thinnews Co., a company that uses...
The following information for the past year is available from Thinnews Co., a company that uses machine hours to apply standard factory overhead cost to outputs: Actual total factory overhead cost incurred $ 30,000 Actual fixed overhead cost incurred $ 7,000 Budgeted fixed overhead cost $ 12,000 Actual machine hours 8,000 Standard machine hours allowed for the units manufactured 4,600 Denominator volume—machine hours 7,500 Standard variable overhead rate per machine hour $ 3 The variable overhead spending variance, to the...