22.
Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.50, its average move time is 0.6 day, and its average queue time is 2.2 days.
Required:
a. What is the wait time? (Round your answer to 1 decimal place.)
b. What is the process time? (Round your answer to 1 decimal place.)
c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)
a | ||||
Delivery cycle time | = | Wait time | + | Throughput time |
36 | = | Wait time | + | 14 |
Wait time | = | 36 | - | 14 |
Wait time | = | 22 Days |
b | ||||
MCE | = | Process time | / | Throughput time |
0.5 | = | Process time | / | 14 |
Process time | = | 7 Days |
c | ||||||||
Throughput time | = | Process time | + | Inspection time | + | Move time | + | Queue time |
14 | = | 7 | + | Inspection time | + | 0.6 | + | 2.2 |
Inspection time | = | 4.2 |
Dear Student,
Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.
Also please give your positive rating.
Get Answers For Free
Most questions answered within 1 hours.