Question

22. Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average...

22.

Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.50, its average move time is 0.6 day, and its average queue time is 2.2 days.

Required:

a. What is the wait time? (Round your answer to 1 decimal place.)

b. What is the process time? (Round your answer to 1 decimal place.)

c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)

Homework Answers

Answer #1
a
Delivery cycle time = Wait time + Throughput time
36 = Wait time + 14
Wait time = 36 - 14
Wait time = 22 Days
b
MCE = Process time / Throughput time
0.5 = Process time / 14
Process time = 7 Days
c
Throughput time = Process time + Inspection time + Move time + Queue time
14 = 7 + Inspection time + 0.6 + 2.2
Inspection time = 4.2


Dear Student,

Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.

Also please give your positive rating.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Schurz Corporation's management reports that its average delivery cycle time is 28 days, its average throughput...
Schurz Corporation's management reports that its average delivery cycle time is 28 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency (MCE) is 0.40, its average move time is 0.6 day, and its average queue time is 3.0 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations and...
Rintharamy Corporation's management reports that its average delivery cycle time is 28 days, its average throughput...
Rintharamy Corporation's management reports that its average delivery cycle time is 28 days, its average throughput time is 8.8 days, its manufacturing cycle efficiency (MCE) is 0.22, its average move time is 0.4 day, and its average queue time is 5.00 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.)         b. What is the process time? (Round your answer to 1 decimal place.)         c. What is the inspection time? (Round your intermediate...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 13.2 Inspection time 0.7 Process time 1.60 Move time 0.6 Queue time 2.2 Required: a. Compute the throughput time.(Enter your answer rounded to 1 decimal...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.9 Inspection time 0.6 Process time 3.8 Move time 0.3 Queue time 3.2 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.3 Inspection time 0.2 Process time 1.4 Move time 1.3 Queue time 2.5 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 14.0 days Process time 2.7 days Move time 1.0 days Queue time 5.0 days Required: 1. Compute the throughput time. 2. Compute the manufacturing...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.0 days Process time 2.5 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
Astro Clothing Company wants to reduce the length of time between a customer placing an online...
Astro Clothing Company wants to reduce the length of time between a customer placing an online order and when that order is actually shipped. Astro Clothing proivdes the following data from operations: Inspection time 0.6 days Wait time (from order to start of production) 15.5 days Process time 3.3 days Move time 1.0 days Queue time 3.8 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.6 days   Wait time (from order to start of production) 16.8 days   Process time 3.5 days   Move time 0.6 days   Queue time 3.9 days Required: 1. Compute the throughput time. (Round your answer to...