Question 5:
Table Q5(a).
Table Q5(a) |
|
Week of Operation |
Probability of failure during the given week |
1 |
0.00 |
2 |
0.15 |
3 |
0.15 |
4 |
0.30 |
5 |
0.40 |
(ii) continued..
Preventive cost should be carried out in week 4 & week 5 because breakdown cost in week 4 & week 5 is more than preventive cost.