Question

Standards kg/hour per unit Materials 12 $7 $84 Direct Labour 3 $30 $90 Monthly production data...

Standards
kg/hour per unit
Materials 12 $7 $84
Direct Labour 3 $30 $90
Monthly production data
Units produced 22,000
Materials Used 203,000 kg
Labour worked 60,000 hours
Material purchased 320,000 kg
Material purchased $2,036,000
Total direct labour variance $2,378 uf
Required:
Actual direct labour rate per hour

Homework Answers

Answer #1
  • Question only asks for ACTUAL DIRECT LABOR HOUR rate.
  • Standard labor hours = 3 hours per unit at $ 30 per hour.

Actual Units = 22,000
Standard hours for actual units = 22,000 units x 3 hours per unit = 66,000 hours
Standard labor cost = 66,000 hours x $ 30 per hour = $ 1,980,000

Hence, standard data for actual 22,000 units:
66000 hours (Standard hours – SH) x $30 per hour (Standard labor rate – SR) = $ 1,980,000 (Standard labor cost)

  • Total Direct Labor Variance = $ 2,378 Unfavourable.

This means that actual labor cost is $ 2,378 more than standard labor cost.

Hence, actual labor cost = Standard labor cost + $ 2,738
= $ 1,980,000 + $ 2,738
= $ 1,982,738.

  • Answer

Actual Labor hour rate = Actual direct labor cost / Actual hours worked
= $ 1,982,738 / 60,000 hours
= $ 33.05 per hours

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Misc. Ltd. has set up the following standards for materials and direct labour for a standard...
Misc. Ltd. has set up the following standards for materials and direct labour for a standard batch of 10,000 units: Direct Materials: 10 kg. per unit @ Rs.30/kg. Direct labour: 1 hr. per unit @ Rs. 20/hr. The number of actual units produced was 9,810. During the month, material purchases amounted to 1,00,000 kg. at a total cost of Rs.31,00,000. The actual rate paid for labour was Rs.21 per hour. Actual inputs used were: 98,073 kgs. of material and 9,800...
Standards for producing one unit of product: Standard Quantity Direct Materials 2lbs Direct labor 2 hours...
Standards for producing one unit of product: Standard Quantity Direct Materials 2lbs Direct labor 2 hours Other data: Materials actually purchased Material price variance Materials actually used to produce 300 units of output Labor efficiency variance Standard Price $1.80 per lbs $18 per hour 4,500 lbs $450 unfavorable 780 lbs $90 unfavorable a. The material purchase price per pound. b. The material quantity variance. c. The actual number of hours worked.
Fabers, Inc. has established the following standards for production: Materials:       Kilograms per unit – 4.3...
Fabers, Inc. has established the following standards for production: Materials:       Kilograms per unit – 4.3 kg       Cost per kilogram – $2.50 Direct Labor:       Hours per unit – 0.7       Cost per hour – $16.50 For the month of August, 50,000 units were produced. Actual results were: Materials:        Total cost – $540,000        Kilograms used – 180,000       Direct Labor:        Total cost – $640,000        Hours used – 40,000        1. What is the materials...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.85 Fixed manufacturing overhead 6.15 Total standard cost per unit $52.00 Actual costs for producing 2,690 units were as follows: Direct materials used 5,920 kg Direct materials purchased (6,730 kg) $32,304 Direct labour (6,950 hours) $67,415 Variable manufacturing costs $32,200 Fixed manufacturing costs $17,700 1....
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard cost per unit $ 105.00 The company planned to produce and sell 19,000 units in March. However, during March the company actually produced and...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per costume12.50yards,, Price per yard $26.00average Direct Labor: D.L. Hours per costume 62.00hours,, D.L. Rate per hour $44.50average Variable MOH standard rate per direct labor hour $4.35per D.L. hour,,Fixed MOH standard rate per direct labor hour $9.47per D.L. hour,,Total Budgeted Fixed MOH (for 1 month) $ 1,250,000 Actual cost and data from the current month: Actual number of yards of materials purchased 28,500 Actual cost...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) $10.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.45 Fixed manufacturing overhead 7.05 Total standard cost per unit $52.50 Actual costs for producing 2,710 units were as follows: Direct materials used 5,990 kg Direct materials purchased (6,440 kg) $30,912 Direct labour (6,820 hours) $68,882 Variable manufacturing costs $32,300 Fixed manufacturing costs $17,600 Calculate...
The following labor standards have been established for a particular product: Standard labor-hours per unit of...
The following labor standards have been established for a particular product: Standard labor-hours per unit of output 2.4 hours Standard labor rate $13.95 per hour The following data pertain to operations concerning the product for the last month:    Actual hours worked 4,300 hours Actual total labor cost $50,720 Actual output 2,900 units What is the labor rate variance for the month? $9,265 F $10,847 F $3,360 F $3,360 U Jackson Industries uses a standard cost system in which direct...
Standards for one unit of product: Direct Materials: 5 pounds at $2 per pound Direct Labor:...
Standards for one unit of product: Direct Materials: 5 pounds at $2 per pound Direct Labor: 0.50 hour at $16 per hour Materials and Labor Used to produce 8,500 units: Direct Materials: 46,000 pounds at $3 per pound Direct Labor: 4,000 hours at ? per hour If the Direct Labor Price Variance is $4,600 Unfavorable, what is the actual labor rate per hour?
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one car cover are as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 9.0 metres of cloth $ 10 per metre $ 90.00   Direct labour 0 hours $ 20 per hour $ 7   Variable overhead 0 hours $ 8 per hour $ 3 Budgeted fixed overhead cost is $17,400, and the normal production volume is 2,885 car covers. Overhead is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT