Martina, Inc. has two service departments (Human Resources and
Building Maintenance) and two production departments (Machining and
Assembly). The company allocates Building Maintenance cost on the
basis of square footage and allocates Building Maintenance first in
step-down method. The square footage occupied by each department
follows.
Human Resources | 16,000 |
Building Maintenance | 23,000 |
Machining | 28,000 |
Assembly | 36,000 |
Assuming use of the direct method, over how many square feet would the Building Maintenance cost be allocated (i.e., spread)?
64,000.
More information is needed to judge.
103,000.
39,000.
80,000.
The answer is - 64000
Machining | 28,000 |
Assembly | 36,000 |
Total Square Feet | 64,000 |
Dear Student,
Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.
Also please give your positive rating.
Get Answers For Free
Most questions answered within 1 hours.